PMI PMR Readiness (Exam 1)

PMI PMR Readiness (Exam 1)

Assessment

Flashcard

Business

9th - 12th Grade

Hard

Created by

Quizizz Content

FREE Resource

Student preview

quiz-placeholder

41 questions

Show all answers

1.

FLASHCARD QUESTION

Front

Two teams working through a project conflict seek a win/win solution. Which conflict strategy should they employ? Options: Compromise/ Reconcile, Force/ Direct, Collaborate/ Problem-Solve, Smooth/ Accommodate

Back

Collaborate/ Problem-Solve

Answer explanation

To achieve a win/win solution, the teams should collaborate and problem-solve, working together to find a mutually beneficial outcome.

2.

FLASHCARD QUESTION

Front

A construction company wants to follow proper processes for projects and their documentation. Which document serves as the official authorization for a project?

Back

Project Charter

Answer explanation

The Project Charter serves as the official authorization for a project, outlining the project objectives, scope, stakeholders, and budget.

3.

FLASHCARD QUESTION

Front

A project to build a new library is behind schedule. Which adjustment to the project plan will have the best chance of putting the schedule back on track? Options: Reducing the number of quality inspections on the building., Adding an additional team of builders to the project., Removing a task to plant the garden., Increasing the project budget by 10%

Back

Removing a task to plant the garden.

Answer explanation

Removing a task to plant the garden will help put the schedule back on track by reducing unnecessary work and focusing on essential project components.

4.

FLASHCARD QUESTION

Front

A project manager receives a suggestion for an app feature that was not part of the original development scoping. What should be the first step taken to add it to the project scope?

Back

Identify a change request.

Answer explanation

Identifying a change request is the first step to add a new feature to the project scope, allowing for proper documentation and evaluation before making any changes.

5.

FLASHCARD QUESTION

Front

Why is closing contracts important in the closing phase of a project?

Back

To ensure work has been completed accurately and satisfactorily.

Answer explanation

The overall purpose of closing contracts in the closing phase is to ensure work has been completed accurately and satisfactorily.

6.

FLASHCARD QUESTION

Front

Which project is utilizing a predictive approach? Options: A garden area that has a defined space and number of plants to be planted, but the time frame of the building of the garden is not set. A science lab to where the specifications of the lab can be defined and adjusted once the core of the lab is built. A building wing where all of the specifications for the classrooms are defined up front and any changes to the specifications have to go through a change control board. A playground with multiple areas, each with its own individual project, with multiple fixed scopes, but the overall project is subject to change.

Back

A building wing where all of the specifications for the classrooms are defined up front and any changes to the specifications have to go through a change control board.

Answer explanation

The project utilizing a predictive approach is the building wing where all specifications for the classrooms are defined upfront, and any changes must go through a change control board.

7.

FLASHCARD QUESTION

Front

Which type of project authority is based on comprehensive respect for a manager's knowledge and leadership abilities, even if the manager is not a subject matter expert on the actual work to be done?

Back

Reverant

Answer explanation

The correct choice is 'Reverant' because this type of project authority is based on respect for a manager's knowledge and leadership abilities, even if they are not subject matter experts.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?