1.

FLASHCARD QUESTION

Front

What is the expected outcome of DfMA 2.0 implementation?

Back

Minimalistic and efficient installation

2.

FLASHCARD QUESTION

Front

Normally, how do we determine the lead contractor for DfMA 2.0 implementation? Options: The Contractor with the most extensive safety measures, The Contractor with the highest number of workers available, The Contractor with the bulkiest services or the most tiers of services, The Contractor with DfMA experience

Back

The Contractor with the bulkiest services or the most tiers of services

3.

FLASHCARD QUESTION

Front

What does DfMA stand for?

Back

Design for Manufacture and Assembly

4.

FLASHCARD QUESTION

Front

What is a key feature of the ATIF (Assembly, Transportation, and Installation Frame) in DfMA 2.0?

Back

Reuse of non-essential steel members for future subsequent modules

5.

FLASHCARD QUESTION

Front

What is one major challenge that remains even with shared bracketry in DfMA 2.0?

Back

Multiple contractors still need to work at height in the same area for containment installation

6.

FLASHCARD QUESTION

Front

How does service zoning in DfMA 2.0 improve coordination?

Back

It provides designated areas for different SWC services, improving organization.

7.

FLASHCARD QUESTION

Front

Currently, do we provide DfMA 2.0 modules for areas where there are services branching into plant rooms?

Back

No. Workers may have difficulty connecting the services due to limited space

8.

FLASHCARD QUESTION

Front

Assuming the module is installed next to a wall, what is the maximum width of a DfMA 2.0 module?

Back

800mm

9.

FLASHCARD QUESTION

Front

What does ATIF stand for?

Back

Assembly, Transportation and Installation Frame