

Chapter 5 - Part 1
Flashcard
•
Professional Development
•
University
•
Practice Problem
•
Hard
Wayground Content
FREE Resource
Student preview

19 questions
Show all answers
1.
FLASHCARD QUESTION
Front
What is risk-based testing?
Back
A test approach which test activities are selected, prioritized, and managed based on risk analysis and risk control.
Answer explanation
According to the syllabus: The test approach, in which test activities are selected, prioritized, and managed based on risk analysis and risk control, is called risk-based testing. (page 50)
2.
FLASHCARD QUESTION
Front
The level of risk is determined by which of the following? Likelihood and impact
Back
Likelihood and impact
Answer explanation
Risk is a potential event, hazard, threat, or situation whose occurrence causes an adverse effect. A risk can be characterized by two factors:
• Risk likelihood – the probability of the risk occurrence (greater than zero and less than one)
• Risk impact (harm) – the consequences of this occurrence
These two factors express the risk level, which is a measure for the risk. The higher the risk level, the more important is its treatment.
3.
FLASHCARD QUESTION
Front
Which of the following is the characteristic of a metrics-based approach for test estimation? Budget which was used by a previous similar test project, Overall experience collected in interviews with test managers, Estimation of effort for test automation agreed in the test team, Average of calculations collected from business experts
Back
Budget which was used by a previous similar test project
Answer explanation
A metrics-based approach for test estimation typically uses historical data from past projects. This could manifest in a variety of metrics such as past budgets, durations, team sizes, or issue counts.
4.
FLASHCARD QUESTION
Front
The ISTQB Foundation Syllabus establishes a fundamental test process where test planning occurs early in the project, while test execution occurs at the end. Which of the following elements of the test plan, while specified during test planning, is assessed during test execution? Exit criteria, Entry criteria, Test tasks, Test team training
Back
Exit criteria
5.
FLASHCARD QUESTION
Front
Consider the following exit criteria which might be found in a test plan:
I. No known customer-critical defects.
II. All interfaces between components tested.
III. 100% code coverage of all units.
IV. All specified requirements satisfied.
V. System functionality matches legacy system for all business rules.
Which of the following statements is true about whether these exit criteria belong in an acceptance test plan?
Back
Only statements I, IV, and V belong in an acceptance test plan.
Answer explanation
An acceptance test plan focuses on validating whether the system meets business requirements and is ready for deployment. The relevant exit criteria should align with user needs, functional expectations, and business goals.
II. All interfaces between components tested. -> relevant to integration testing
III. 100% code coverage of all units. -> typically a unit testing criterion
6.
FLASHCARD QUESTION
Front
In prioritizing what to test, the MOST important objective is to: Obtain good test coverage, Test high risk areas, Find as many faults as possible, Test whatever is easiest to test
Back
Test high risk areas
7.
FLASHCARD QUESTION
Front
Your team uses the three-point estimation technique to estimate the test effort for a new high-risk feature. The following estimates were made:
- - most optimistic estimation: 4 person-hours
- - most likely estimation: 13 person-hours
- - most pessimistic estimation: 10 person-hours
Back
11 person-hours
Answer explanation
E = (a + m*4 + b)/6 = (4 + 13*4 + 10)/6 = 11
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?