Project Management Budget and Performance Metrics
Flashcard
•
Business
•
Professional Development
•
Hard
Rhosecel Valerio
FREE Resource
Student preview

13 questions
Show all answers
1.
FLASHCARD QUESTION
Front
Budget at Completion (BAC)
Back
Original budget of the project.
2.
FLASHCARD QUESTION
Front
Planned Value (PV)
Back
Amount of money worth of work that should have been done on the project. PV = Planned % Complete x BAC
3.
FLASHCARD QUESTION
Front
Earned Value (EV)
Back
Amount of money worth of work actually done on the project. EV = Actual % Complete x BAC
4.
FLASHCARD QUESTION
Front
Actual Cost (AC)
Back
Amount of money already spent on the project.
5.
FLASHCARD QUESTION
Front
Cost Variance (CV)
Back
The difference between the work done and money spent. CV = EV - AC. Positive for under budget, negative for over budget.
6.
FLASHCARD QUESTION
Front
Cost Performance Index (CPI)
Back
The rate of spending to earning on the project. CPI = EV / AC. Should be 1 or over for projects under budget.
7.
FLASHCARD QUESTION
Front
Schedule Variance (SV)
Back
The difference between the amount of work planned and actually done. SV = EV - PV. Positive for ahead of schedule, negative for behind schedule.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?