1.

FLASHCARD QUESTION

Front

What is a deliverable?

Back

A unique output of a project

2.

FLASHCARD QUESTION

Front

Your customer states that the packaging for the new product being developed must be easy for everyone to open. During product testing, only 60% of the people were able to open the packaging easily. As the project manager, what should you do?

Back

Request a team meeting to decide on corrective action.

3.

FLASHCARD QUESTION

Front

What is a project life cycle?

Back

The series of phases that a project passes through from its start to its completion.

4.

FLASHCARD QUESTION

Front

What is a benefit of creating a lessons learned document?

Back

Sharing best practice approaches among the team members

5.

FLASHCARD QUESTION

Front

What is a key characteristic of the adaptive project management approach? A. Continuous refinement of the product based upon stakeholder feedback, B. Minimal changes due to familiarity with project requirements, C. Sequential completion of tasks with no change in scope, D. Delivery of the product after the final phase has been completed

Back

Continuous refinement of the product based upon stakeholder feedback

6.

FLASHCARD QUESTION

Front

What should you do if a product feature is out of scope?

Back

You should decline the development of the feature.

7.

FLASHCARD QUESTION

Front

What role does quality assurance play in the project development process?

Back

It ensures procedures are followed to meet standards for performance.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?