1.

FLASHCARD QUESTION

Front

What should John do to mitigate the issue of a possible delay due to the requirement to add 100 cameras and 300 access control points to the project?

Back

Analyse the request and then communicate the impact of the change and the alternative, if any exist. If the change is inevitable, ensure that the stakeholders understand how the change affects the schedule, cost, scope and quality of the project.

2.

FLASHCARD QUESTION

Front

Identify the type of risk: "To outsource risky jobs to another company and sharing the risk together."

Back

Risk Sharing

3.

FLASHCARD QUESTION

Front

Identify the type of risk: “The acceptance of the burden of loss, or benefit of gain, from a particular risk.”

Back

Risk Retention

4.

FLASHCARD QUESTION

Front

Determine the duration for the pessimistic days given: PERT weight average = 20 days, optimistic duration = 15 days, most likely duration = 20 days.

Back

25 days

5.

FLASHCARD QUESTION

Front

Actual Cost (AC) = $100,000, Planned Value (PV) = $50,000, Earned Value (EV) = $120,000. Determine the Cost Variance (CV).

Back

$20,000

6.

FLASHCARD QUESTION

Front

Actual Cost (AC) = $100,000, Planned Value (PV) = $50,000, Earned Value (EV) = $120,000. Determine the Schedule Variance (SV).

Back

$70,000

7.

FLASHCARD QUESTION

Front

Given the following values, Actual Cost (AC) = $100,000 Planned Value (PV)=$50,000 Earned Value (EV)=$120,000, determine the Schedule Performance Index (SPI)?

Back

2.4

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?