2021 IPC CHAPTER 1
Flashcard
•
Construction
•
Professional Development
•
Practice Problem
•
Hard
Wayground Content
FREE Resource
Student preview

13 questions
Show all answers
1.
FLASHCARD QUESTION
Front
How many extensions of 180 days may a code official grant on an application for a permit?
Back
one or more
2.
FLASHCARD QUESTION
Front
Where, in any specific case, different sections of this code specify different materials, methods of construction or other requirements, the most ____________ shall govern.
Back
restrictive
3.
FLASHCARD QUESTION
Front
Where there are practical difficulties involved in carrying out the provisions of this code, the code official shall have the authority to grant ______________ for individual cases.
Back
modifications
4.
FLASHCARD QUESTION
Front
Underground inspection shall be made after trenches or ditches are excavated and bedded, piping installed, and before any ______________ is put in place.
Back
backfill
5.
FLASHCARD QUESTION
Front
Where the extent of a referenced standard includes subject matter that is within the scope of the IPC, the provisions of ____________________ shall take precedence over the provisions in the referenced standard.
Back
the IPC
6.
FLASHCARD QUESTION
Front
Rough-in inspection shall be made after the roof, framing, fireblocking, firestopping, draftstopping and bracing is in place and all sanitary, storm and water distribution piping is roughed-in, and prior to the installation of ____________ or ____________ membranes.
Back
wall, ceiling
7.
FLASHCARD QUESTION
Front
The purpose of this code is to establish __________ standards to provide a reasonable level of safety, health, property protection and public welfare.
Back
minimum
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Microsoft
or continue with
%20(1).png)
Apple
Others
Already have an account?