
Unit 307 Session 9 Testing cold water systems
Presentation
•
Mathematics
•
1st Grade
•
Practice Problem
•
Easy
Plumbers Cymoedd
Used 9+ times
FREE Resource
14 Slides • 18 Questions
1
Testing cold water systems
Testing and commissioning procedures
Testing of installations is the first time we see whether the installation is watertight.
For pressure systems and sanitary systems, testing procedures are set out in the relevant British Standards and Regulations
2
Pre-testing checks Before commissioning takes place:
● walk around the installation; check that you are happy that the installation is correct and meets installations standards
● check that all open ends are capped off and all valves isolated
● check that all capillary joints are soldered and that all compression joints are fully tightened
● check that sufficient pipe clips, supports and brackets are installed, and that all pipework is secure.
3
Testing procedures
Testing procedures differ depending on the type of pipework installed.
The process involves filling the system with water to a specific pressure, letting it stand for a period of time to temperature stabilise and then checking it for pressure loss. Here, we will look at those different testing procedures.
Hot and cold water systems testing is detailed in BS 6700.
● Copper tubes and low carbon steel pipes: systems installed in copper tube and low carbon steel pipes should be tested to 1.5 times normal operating pressure.
They should be left for a period of 30 minutes to allow for temperature stabilisation and then left for a period of one hour with no visible pressure loss
4
5
There are different tests for other pipework types, BS6700 gives 2 tests for plastic pipework.
Use the link below, look through the BS6700 document page's 57-59 and answer the questions on the next slides.
6
Open Ended
Describe test 'A' (Do not copy and paste)
7
Open Ended
Describe test 'B' (Do not copy and paste)'
8
Open Ended
What is the main difference you noticed between the tests for plastic pipework and that for ridgid (copper or L.C.S) pipework?
9
Commissioning
Commissioning is the part of the installation where the system is filled and run for the first time. It is when we see if it works as designed.
The first task is to fill the system and check for leaks at the appliances. This is best carried out in stages so that sections of the installation, i.e. cold water, hot water, central heating, can be filled and tested separately.
At each stage of the filling process, the system should be checked for leaks before moving on to the next section.
Once the systems have been filled they should be drained down and flushed through with clean water, then refilled.
The water levels in WC cisterns, cold water storage cisterns, and feed and expansion cisterns (if fitted) should be checked for compliance with the relevant regulations.
10
Check the flow rates at all taps to see if they deliver the flow rates demanded by the manufacturer’s literature, and check the operation of all controls, including thermostats and motorised valves.
11
12
To convert from litres per second (l/s) to litres per minute (l/m), simply multiply the l/s by 60.
For example:
0.3 l/s = 0.3 × 60 = 18 l/m
To convert from litres per minute
(l/m) to litres per second (l/s),
simply divide the l/m by 60.
For example:
25 l/m = 25 ÷ 60 = 0.41 l/s
Water flow rate is measured in litres per second or litres per minute.
13
Multiple Choice
Convert 30 l/m into l/s
0.5 l/s
0.10 l/s
5.0 l/s
50 l/s
14
Multiple Choice
Convert .25 l/s into l/m
15 l/m
1.5 l/m
0.15 l/m
150 l/m
15
Multiple Choice
Convert 12 l/m to l/s
0.2 l/s
2.0 l/s
20 l/s
200 l/s
16
Multiple Choice
Convert 0.12 l/s to l/m
7.2 l/m
.72 l/m
72 l/m
720 l/m
17
PLANNED AND UNPLANNED MAINTENANCE
Maintenance tasks on cold water services, appliances and valves are essential to ensure the continuing correct operation of the system.
The term used when isolating a water supply during maintenance operations is ‘temporary
decommissioning’.
Before undertaking the repair or replacement of components, we must first ascertain what the problem is.
The customer will be able to tell you what is happening with the component. They may not know the technical language but they will be able to explain the problem well enough for you to understand.
18
Maintenance
There are basically two types of maintenance:
1. planned preventative maintenance
2. unplanned/emergency maintenance.
19
Open Ended
What do you think is meant by 'planned preventative maintenance'?
20
Planned preventative maintenance (PPM)
Planned preventative maintenance is usually performed on larger systems and commercial/industrial installations.
It is performed to a pre-arranged maintenance schedule, which may mean out-of-hours working if the supply of water cannot be disrupted during normal working hours.
It is designed to stop problems from occurring by catching faults in their early stages.
Planned preventative maintenance could include:
periodic system inspection – checking for leaks
re-washering of float-operated valves
re-washering and re-seating of terminal fittings and taps
inspection and cleaning of cisterns
readjustment of water levels in cisterns
re-washering of drain valves
cleaning of filters and strainers
maintenance of water softeners
checking the correct operation of stop valves
checking flow rates at all outlets.
21
A record of all repairs and maintenance tasks completed will need to be recorded on the maintenance schedule at the time of completion, including their location, the date when they were carried out and the types of test performed.
This will ensure that a record of past problems is kept for future reference.
22
Open Ended
Give some examples of what you think would be classed as unplanned/emergency maintenance
23
Unplanned and emergency maintenance
Unplanned and emergency maintenance occur when a fault suddenly develops, such as a burst pipe, or a small problem suddenly becomes a larger issue, such as a dripping tap or sudden loss of water.
Unplanned and emergency maintenance can include:
burst pipes and leaks
running overflows
dripping taps
loss of low-pressure, cistern-fed cold water supply due to faulty float-operated valves
poor past installation practices, such as incorrectly positioned overflow pipes
complete component breakdown necessitating the replacement of the component.
24
Multiple Choice
According to BS 6700, what is the recommended testing pressure for hot and cold water systems installed in copper tubes and low carbon steel pipes?
Normal operating pressure
Twice the normal operating pressure
1.5 times normal operating pressure
Three times normal operating pressure
25
Multiple Choice
What is the primary purpose of commissioning in the installation process?
Filling the system with water
Identifying leaks at appliances
Checking the operation of components and controls
Checking pipework clipping
26
Multiple Choice
During commissioning, why is it advisable to fill and test different sections of the installation separately?
To save water
To identify leaks more efficiently
To speed up the process
To comply with regulations
27
Multiple Choice
What is the term used when isolating a water supply during maintenance operations?
Permanent decommissioning
Emergency decommissioning
Temporary decommissioning
Planned decommissioning
28
Multiple Choice
Which type of maintenance is usually performed on larger systems and commercial/industrial installations with a pre-arranged schedule?
Emergency maintenance
Unplanned maintenance
Planned preventative maintenance (PPM)
Reactive maintenance
29
Multiple Choice
What is one of the tasks involved in planned preventative maintenance?
Emergency component replacement
Periodic system inspection
Temporary decommissioning
Unplanned maintenance
30
Multiple Choice
When does unplanned and emergency maintenance typically occur?
On a pre-arranged schedule
During commissioning
When faults are caught in early stages
When a fault suddenly develops
31
Multiple Choice
What might be a scenario for unplanned and emergency maintenance?
Periodic system inspection
Burst pipes and leaks
Checking flow rates at outlets
Cleaning of filters and strainers
32
Multiple Choice
Why is planned preventative maintenance important?
To identify possible faults in their early stages
To perform emergency repairs
To decommission the system temporarily
To identify leaks during commissioning
Testing cold water systems
Testing and commissioning procedures
Testing of installations is the first time we see whether the installation is watertight.
For pressure systems and sanitary systems, testing procedures are set out in the relevant British Standards and Regulations
Show answer
Auto Play
Slide 1 / 32
SLIDE
Similar Resources on Wayground
25 questions
Physical and Chemical Changes Review
Presentation
•
8th Grade
22 questions
Similar Figures, find scale factor and solve for missing sides
Presentation
•
KG
24 questions
properties of addition
Presentation
•
1st Grade
25 questions
Library Y1
Presentation
•
1st Grade
23 questions
Let's Make Ten
Presentation
•
1st - 2nd Grade
27 questions
Math Study Guide III Partial
Presentation
•
1st Grade
21 questions
Interpret Data
Presentation
•
1st Grade
Popular Resources on Wayground
5 questions
A Home on the Shore
Quiz
•
3rd Grade
28 questions
US History Regents Review
Quiz
•
11th Grade
6 questions
A Horse Tale
Quiz
•
3rd Grade
20 questions
Math Review
Quiz
•
3rd Grade
10 questions
Juneteenth History and Significance
Interactive video
•
5th - 8th Grade
20 questions
Dividing Fractions
Quiz
•
5th Grade
55 questions
A Long Walk to Water Final Review
Quiz
•
6th - 8th Grade
10 questions
Equation Word Problems
Quiz
•
7th Grade