PMP Prep_Project Scope Mgmt.

PMP Prep_Project Scope Mgmt.

University

10 Qs

quiz-placeholder

Similar activities

Product Based Planning (PBP) Quiz

Product Based Planning (PBP) Quiz

12th Grade - University

12 Qs

Chapter 15

Chapter 15

University

15 Qs

Business Improvement Techniques

Business Improvement Techniques

University

10 Qs

ITOD L3: Exploring Mind Maps and Scope Maps

ITOD L3: Exploring Mind Maps and Scope Maps

12th Grade - University

10 Qs

PPE

PPE

University

11 Qs

D1. Planificación y estrategia de riesgos

D1. Planificación y estrategia de riesgos

University

10 Qs

PMP - Time

PMP - Time

University

10 Qs

Project Organisation Structure

Project Organisation Structure

University

7 Qs

PMP Prep_Project Scope Mgmt.

PMP Prep_Project Scope Mgmt.

Assessment

Quiz

Professional Development

University

Hard

Used 10+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The project manager for a design project is using the Define Scope process. Which BEST describes this?
Creating a document that lists all of the features of the product
Creating a plan for managing changes to the scope baseline
Creating a document that describes all of the work the team does to make the deliverables
Creating a graphical representation of how the phases or deliverables decompose into work packages

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following BEST describes the purpose of the project scope statement?
It describes the features of the product of the project
It is created before the scope management plan
It decomposes deliverables into work packages
It describes the objectives, requirements, and deliverables of the project, and the work needed to create them

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During which part of project management process is the project scope statement created ?
Initiating
Planning
Executing
Monitoring and control

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is an output of the Collect Requirements process?
Requirements Traceability Matrix
Project Scope statement
Work breakdown structure
Change requests

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The preparation of scope baseline can be BEST described as involving
the functional managers
The project team
All the stakeholders
The project expediter

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following correctly depicts the most common order in which the project management processes are executed?
Validate Scope is done before Control Quality
Perform Quality Assurance is done after Validate Scope
Control Quality is done before Validate Scope
Control Quality is done after Close Project or Phase

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

As the Project Manager for Midway Carnival Rides, you are starting off on the Define Scope process. Which of the following is a key input to the process?
Risk Management Plan
Quality Management Plan
Project Charter
Staffing Management Plan

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?