1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The project manager for a design project is using the Define Scope process. Which BEST describes this?

Creating a document that lists all of the features of the product
Creating a plan for managing changes to the scope baseline
Creating a document that describes all of the work the team does to make the deliverables
Creating a graphical representation of how the phases or deliverables decompose into work packages

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following BEST describes the purpose of the project scope statement?

It describes the features of the product of the project
It is created before the scope management plan
It decomposes deliverables into work packages
It describes the objectives, requirements, and deliverables of the project, and the work needed to create them

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During which part of project management process is the project scope statement created ?

Initiating
Planning
Executing
Monitoring and control

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is an output of the Collect Requirements process?

Requirements Traceability Matrix
Project Scope statement
Work breakdown structure
Change requests

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The preparation of scope baseline can be BEST described as involving

the functional managers
The project team
All the stakeholders
The project expediter

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following correctly depicts the most common order in which the project management processes are executed?

Validate Scope is done before Control Quality
Perform Quality Assurance is done after Validate Scope
Control Quality is done before Validate Scope
Control Quality is done after Close Project or Phase

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

As the Project Manager for Midway Carnival Rides, you are starting off on the Define Scope process. Which of the following is a key input to the process?

Risk Management Plan
Quality Management Plan
Project Charter
Staffing Management Plan

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?