1.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
Complete the list of group decision-making techniques: Unanimity, Majority, Consensus, Plurality...
2.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
A project manager has been managing a project for six months and is nearing completion of the project; however, change requests are still pouring in. The project is ahead of schedule but over budget Which of the following statements is TRUE?
3.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
Which of the following statements is TRUE concerining functionality that is over and above the documented scope?
4.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
Which of the following activities is done FIRST?
5.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
You are the project manager for a large construction project, and you identify two key areas where changing the scope of the product would deliver significantly higher value or the customer. Which of the following options is MOST correct?
6.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
A large defense contractor to the government is facilitating an inspection of their project's product with their customer when the customer notices a feature that was not requested or documented. The project manager for the defense contractor points out that this feature adds significant value, but the customer is concerned that it may also introduce risk. Can the customer accept the product?
7.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
Sara and Eric are two project managers having a discussion about which metrics to use to gauge project performance. They agree that benchmarking is a preferred approach, but Eric maintains that the best metrics should come from industry standards published by their industry group. Sara believes that they should benchmark within their own organization to see how well other departments are performing and base their own projections from those. In the context of their discussion, which of the following is true?
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
54 questions
Analyzing Line Graphs & Tables
Quiz
•
4th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade
Discover more resources for Professional Development
20 questions
Place Value
Quiz
•
KG - 3rd Grade
6 questions
3.3 Magnets
Quiz
•
KG
20 questions
Ch. 7 Quadrilateral Quiz Review
Quiz
•
KG - University
12 questions
HOMOPHONES
Lesson
•
KG - 4th Grade
10 questions
Long i- igh, ie, and y Quiz
Quiz
•
KG - 3rd Grade
12 questions
Quarter Past, Half Past, and Quarter To
Quiz
•
KG - 12th Grade
20 questions
Capitalization in sentences
Quiz
•
KG - 4th Grade
14 questions
Reference Sources
Lesson
•
KG - 3rd Grade