Hot Water 3

Hot Water 3

University

15 Qs

quiz-placeholder

Similar activities

environmental education

environmental education

University

10 Qs

GLS290 Aerial Camera

GLS290 Aerial Camera

University

10 Qs

Rehab 105 Short Quiz 4 - Endterms

Rehab 105 Short Quiz 4 - Endterms

University

20 Qs

CCHU5001_Week 3_Quiz

CCHU5001_Week 3_Quiz

University

10 Qs

Freight Rate

Freight Rate

University

16 Qs

Project mc²

Project mc²

2nd Grade - Professional Development

11 Qs

Statistics Quiz

Statistics Quiz

University

20 Qs

JOINTS AND MOVEMENTS

JOINTS AND MOVEMENTS

University

10 Qs

Hot Water 3

Hot Water 3

Assessment

Quiz

Other

University

Practice Problem

Medium

Created by

Steve Endicott

Used 344+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which one of the following pieces of information will be provided by the installation plan?

The dwelling position on the estate
The expected completion date
The order in which work should take place
The position of the hot water pipes and valves in a dwelling

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The water supply (water fittings) regulations 1999 lay down

The guidance for good practice when installing hot and cold pipework in adwelling
The regulations covering all internal and external hot and cold watersystems for dwellings
The regulations that cover hot water systems only
The guidance for internal hot and cold water systems only within a dwelling.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which one of the following hot water components should be fixed using flexible connections?

Booster pump for a shower
Indirect hot water cylinder
Shower mixer valve
External bib tap

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A rigid pipework hot water system has a working pressure of 4bar. At what pressure should the pipework be tested for soundness?

1bar for 60 minutes
1½ times the working pressure for 15 minutes
4bar for 30mins then 6bar for 15 minutes
6 bar for one hour

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

To prevent electrolytic corrosion taking place in a system, where can the magnesium rod be placed?

The cold water storage cistern
The hot water cylinder
The circulator
The open vent 

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Guidance on the installation procedures for domestic hot water systems can be found in:

Domestic Water Act 2007
Specification of work
BS6700
Local Authority Regulations

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a customer’s property, the CWSC supplies both the hot and cold water systems. The minimum size of this cistern is:

Equal to 48 hours’ worth of water
230 litres
100 litres
Twice the size of the domestic hot water cylinder 

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?