PMI-ACP Continuous Improvment

Professional Development, Other

University - Professional Development

Used 4+ times

PMI-ACP Continuous Improvment
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In the first part of a retrospective, a team has identeified a number of preoblems. What sequence of steps should they follow to explore and solve those problems?

Generate insights, gather data, decide what to do
Gather data, generate insights, decide what to do
Decide what to do, gather data, generate insights
Decide what to do, generate insights, gather data

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Your team spends 10 minutes waiting for people to turn up for the daily standup meeting which then lasts 15 minutes. The stand-up meeting is then followed by another 5 minutes of the team discussing the hockey game last night, and yet another 5 minutes brainstorming issues to solve. Calculate the ttal cycle time of this process, assuming that the hockey discussion is not categorized as a value-added activity.

15 minutes
20 minutes
30 minutes
35 minutes

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

When generating insights in a retrospective, we ask "why" five times to:

Move beyond our automatic, habitual answers and get to the root cause of an issue.
Get past the denial and resistance that tend to occur in the fierst three r four answers.
Gather five levels of data around the issue.
Avoid aksing "why" six times, since that would be overkill

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is a form of agile review?

Sprints
Customer demos
Unit testing
Project pre-mortems

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What are some of the techniques a team can use to decide what to do about the issues they've identified in a retrospective?

SMART Subjects, Short Goals, Retrospective Planning Games
SMART Games, Retrospective Poker Game, Circle of Goals
Short Subjects, SMART Goals, Retrospective Planning Game
Retrospective Poker Game, Short Subjects, Circle of Questions

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In agile, the kaizen approch involves:

Continuous, incremental improvements recommended by process experts
Bold, top-down re-engineering initiatives
Small, incremental improvements by the people who are doing the work
Stopping the process as needed to implement essential improvements

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You have been asked to review an agile team's recently enhanced methodology to assess its effectiveness. The desireable characteristics that you should be looking for include:

A preference for rapid communications, significant process weight, recommendations for larger teams to use lighter methods
A preference for digital communications, not too much process weight, recommendations for larger teams to use simpler methods
A preference for relevant communications, significant process weight, recommendations for larger teams to use heavier methods
A preference for face-to-face communications, not too much process weight, recommendations for larger teams to use heavier methods.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?