PMP PROJECT STAKEHOLDER MANAGEMENT

PMP PROJECT STAKEHOLDER MANAGEMENT

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

Janice Lopez

Used 32+ times

FREE Resource

Student preview

quiz-placeholder

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Stakeholders are:

The project engineers who design and construct the project.

The people, groups,or organizations that could impact or be impacted by a decision,activity,or outcome of the project.

The organization's corporate attorneys.

The individuals or agencies that control contingency funds and their disbursement through the project management office (PMO).

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is NOT a process in Project Stakeholder Management?

Identify Stakeholders.

Control Stakeholder Engagement.

Monitor Stakeholder Engagement.

Manage Stakeholder Engagement.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

To increase the chances of achieving project success, the project manager should do all of the following EXCEPT:

Identify the stakeholders early in the project or phase.

Analyze the stakeholders levels of interest and individual expectations as well as their importance and influence.

As much as possible, create conflicts among various stakeholders to allow the project team to get optimal work done.

Communicate and work with stakeholders to meet their needs/expectations.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are developing management strategies to effectively engage stakeholders throughout the project life cycle, based on the analysis of their needs, interests, and potential impact on project success. This is known as:

Manage Stakeholder Engagement.

Monitor Stakeholder Engagement.

Plan Stakeholder Engagement.

Plan Stakeholder Management.

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are involved in the process of communicating and working with stakeholders to meet their needs/expectations, address issues as they occur, and foster appropriate stakeholder engagement in project activities throughout the project life cycle. This is known as:

Manage Stakeholder Engagement.

Monitor Stakeholder Engagement.

Plan Stakeholder Management.

Plan Stakeholder Engagement

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are monitoring overall project stakeholder relationships and adjusting strategies and plans for engaging stakeholders. This is known as:

Manage Stakeholder Engagement

Plan Stakeholder Engagement

Stakeholders' Relationship Engagement

Monitor Stakeholder Engagement

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In developing a stakeholder register, you need to include all of the following EXCEPT:

Identification information

Assessment information

Stakeholder classification

Project risk information

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?