PMP -Integration/Scope (Situations)-Exam#18
Authored by Yamil Vigo
Professional Development
University

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
12 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Julia is managing a complex industrial process re-engineering project. She has identified all of her key project stakeholders and has conducted individual interviews with them to identify other project stakeholders as well. However, Julia is still not comfortable with her project's stakeholders list as she believes there would be more key external stakeholders still missing from the list. What can help Julia in this situation?
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Shawn is in the execution phase of his project. He is getting unexpected requests from his stakeholders about the project progress. All of the following can be used by Shawn to respond to their requests EXCEPT:
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Tom is managing a software development project. The buyer of the product is an external entity. During the execution of the project, Tom finds out that a new operations manager has been hired in the customer organization. The new manager is now a key stakeholder of the project. Which of the following documents is least likely to get updated as a result of the addition of this new stakeholder?
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Nancy can bid on two projects. 'Project A' has a 50% return on investment, while the 'Project B' has 20% return on investment. The Project A's scope of work is complex and Nancy's organizations doesn't have the necessary skills and experience to perform this project. However, Project B's scope of work falls within the strengths of Nancy's organizations. Which project must Nancy bid on?
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Your organization has recognized a need to replace the legacy manufacturing system with a modern software application to reduce delivery delays and process downtime. Your IT director anticipates a project to fulfill this business need, however, he warns that the new project's budget cannot exceed $75,000 due to shortages in the department budget. He also indicates that no additional staff will be allocated to this project other than the existing IT staff. If you are assigned as a project manager to this project, you would document these initial project conditions as:
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
You have just received notice that the organization you've been working for as a project manager has gone bankrupt. All employees have been given 72 hours notice of termination. What is the best course of action for the two projects you are managing?
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Jen works as a project manager for the National weather agency. She has been managing a project which was designed to find the impact of climate changes on Northern mountains. The initial study established two months delay for the testing equipment to reach mountains due to road construction. However, a recent assessment has shown a significant drop in the delay time because of rapid progress in construction. Which of the following steps should Jen take next to account for the change in the delay time?
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
29 questions
Alg. 1 Section 5.1 Coordinate Plane
Quiz
•
9th Grade
22 questions
fractions
Quiz
•
3rd Grade
11 questions
FOREST Effective communication
Lesson
•
KG
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
Discover more resources for Professional Development
11 questions
FOREST Effective communication
Lesson
•
KG
20 questions
Place Value
Quiz
•
KG - 3rd Grade
10 questions
Sound Energy Assessment
Quiz
•
KG - 2nd Grade
10 questions
Dr. Seuss
Quiz
•
KG - 5th Grade
20 questions
greater than less than equal to
Quiz
•
KG - 1st Grade
6 questions
Copy of G5_U6_L3_22-23
Lesson
•
KG - Professional Dev...
20 questions
Capitalization in sentences
Quiz
•
KG - 4th Grade
15 questions
Simple Patterns AB, ABB, ABC
Quiz
•
KG - 1st Grade