Search Header Logo

PMP - PROJECT COST MANAGEMENT

Authored by Pedro Pablo Rosa

Professional Development

Professional Development

Used 7+ times

PMP - PROJECT COST MANAGEMENT
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The cost management plan has all of the following characteristics, EXCEPT:

It is based on project cost estimates and is separate from the project management plan.

It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken.

It may specify the level of precision, which is the degree to which activity cost estimates will be rounded up or down.

It describes how the project costs will be planned, structured, and controlled.

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

All of the following are true about cost estimates EXCEPT:

Cost estimates are generally expressed in units of some currency (i.e., dollars, euros, yen, etc.), although in some instances other units of measure, such as staff hours or staff days, are used to facilitate comparisons by eliminating the effects of currency fluctuations.

Costs are estimated for all resources that will be charged to the project.

Information in the risk register should not be considered in cost estimates, because risks can be either threats or opportunities and their impacts tend to balance out.

A cost estimate is a quantitative assessment of the likely costs for resources required to complete the activity. Cost estimates may be presented at the activity level or in summary form.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Analogous cost estimating:

Integrates bottom-up estimating techniques with relevant statistical relationships to estimate the cost of the current project.

Relies on the actual cost of previous, similar projects as the basis for estimating the cost of the current project.

ls used most frequently in the later phases of a project.

Summarizes estimates for individual work packages to estimate the cost of the current project.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The cost performance baseline has all of the following characteristics, EXCEPT:

It is the approved version of the time-phased project budget, excluding any management reserves, and is used as a basis for comparison with actual results

It shows the actual cost expenditures throughout the project life cycle.

It is developed as a summation of the approved budgets for the different schedule activities

It is typically displayed in the form of an S-curve.

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Project cost control includes all of the following, EXCEPT:

Informing appropriate stakeholders of all approved changes and associated costs.

Monitoring cost performance to isolate and understand variances from the approved cost baseline.

Influencing the factors that create changes to the authorized cost baseline.

Allocating the overall estimates to individual work packages to establish a cost baseline.

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The estimate at completion (EAC) is typically based on:

The actual costs incurred for work completed (AC), and the estimate to complete (ETC) the remaining work.

The actual costs incurred for work completed (AC) and the cumulative cost performance index (CPI).

The earned value (EV) and the actual cost for work completed (AC).

The cost performance index (CPI) and the cost variance (CV).

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Your earned value management analysis indicates that your project is falling behind its baseline schedule. You know this because the cumulative EV is much:

Higher than the cumulative AC.

Higher than the cumulative PV.

Lower than the cumulative PV.

Lower than the cumulative CPI.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?