
PMP - PROJECT COST MANAGEMENT
Authored by Pedro Pablo Rosa
Professional Development
Professional Development
Used 7+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The cost management plan has all of the following characteristics, EXCEPT:
It is based on project cost estimates and is separate from the project management plan.
It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken.
It may specify the level of precision, which is the degree to which activity cost estimates will be rounded up or down.
It describes how the project costs will be planned, structured, and controlled.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
All of the following are true about cost estimates EXCEPT:
Cost estimates are generally expressed in units of some currency (i.e., dollars, euros, yen, etc.), although in some instances other units of measure, such as staff hours or staff days, are used to facilitate comparisons by eliminating the effects of currency fluctuations.
Costs are estimated for all resources that will be charged to the project.
Information in the risk register should not be considered in cost estimates, because risks can be either threats or opportunities and their impacts tend to balance out.
A cost estimate is a quantitative assessment of the likely costs for resources required to complete the activity. Cost estimates may be presented at the activity level or in summary form.
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Analogous cost estimating:
Integrates bottom-up estimating techniques with relevant statistical relationships to estimate the cost of the current project.
Relies on the actual cost of previous, similar projects as the basis for estimating the cost of the current project.
ls used most frequently in the later phases of a project.
Summarizes estimates for individual work packages to estimate the cost of the current project.
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The cost performance baseline has all of the following characteristics, EXCEPT:
It is the approved version of the time-phased project budget, excluding any management reserves, and is used as a basis for comparison with actual results
It shows the actual cost expenditures throughout the project life cycle.
It is developed as a summation of the approved budgets for the different schedule activities
It is typically displayed in the form of an S-curve.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Project cost control includes all of the following, EXCEPT:
Informing appropriate stakeholders of all approved changes and associated costs.
Monitoring cost performance to isolate and understand variances from the approved cost baseline.
Influencing the factors that create changes to the authorized cost baseline.
Allocating the overall estimates to individual work packages to establish a cost baseline.
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The estimate at completion (EAC) is typically based on:
The actual costs incurred for work completed (AC), and the estimate to complete (ETC) the remaining work.
The actual costs incurred for work completed (AC) and the cumulative cost performance index (CPI).
The earned value (EV) and the actual cost for work completed (AC).
The cost performance index (CPI) and the cost variance (CV).
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Your earned value management analysis indicates that your project is falling behind its baseline schedule. You know this because the cumulative EV is much:
Higher than the cumulative AC.
Higher than the cumulative PV.
Lower than the cumulative PV.
Lower than the cumulative CPI.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?