Phases of the project life cycle
Authored by david alex
Computers
7th Grade
Used 99+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
what stage is this "fourth phase of the project life cycle. It includes releasing the final work to the customer, handing over project documentation to the business, and sharing project closure to all stakeholders"
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What are the stages of the Project Life Cycle?
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does PLC stand for?
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which phase of the project life cycle needs the most resources?
Initiating
Planning
Executing
Evaluation
5.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
What are the inputs of the initiation phase? Two correct answers
Feasibility report
Constraints list
User requirements
User constraints
6.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
What are the outputs of the planning stage ? Three correct answers
Project plan
Test plan
Feasibility report
Constraints list
7.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
What is input into the execution phase? Three correct answers
Project plan
Test plan
Constraints list
User documentation
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?