Project management

Project management

University

10 Qs

quiz-placeholder

Similar activities

CC105 Quiz No 2 - Final Term

CC105 Quiz No 2 - Final Term

University

10 Qs

 Project Management

Project Management

University

15 Qs

UED 3

UED 3

University

10 Qs

Digital Project Planning

Digital Project Planning

University

12 Qs

SADSIGN Week 3 Quiz

SADSIGN Week 3 Quiz

12th Grade - University

15 Qs

System Analysis and Design Ch 3

System Analysis and Design Ch 3

University

5 Qs

MS PROJECT - MODULE 1

MS PROJECT - MODULE 1

University - Professional Development

10 Qs

Gantt Chart

Gantt Chart

University

10 Qs

Project management

Project management

Assessment

Quiz

Computers

University

Hard

Used 216+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is not part of the functions involved in project management?

Directing

Controlling

Documenting

Scoping

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Uncontrolled addition of technical features to a system :

Scope creep

Constraints

Interruptions

Feature creep

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An inter-task dependency in which two tasks must finish at the same time is called :

Start-to-finish (FS)

Finish-to-start (FS)

Finish-to-finish (FF)

Start-to-start (SS)

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Graphical tool used to depict the hierarchical decomposition of the project into phases,activities, and tasks :

Pert chart

Gannt chart

Activity on arrow diagram

Work break down structure

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the project management charts is most effective when you want to study the relationship between tasks?

Pert chart

Gannt chart

WBS chart

Network chart

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A narrative description of the work to be performed as part of a project :

Scope definition

Statement of work

Resource leveling

progress report

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A model-based technique for estimation wherein standard parameters based on prior projects are applied to the new project is referred to as :

Decomposition

COCOMO

Reverse engineering

Function points

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?