PMP 6th Edition

PMP 6th Edition

Professional Development

65 Qs

quiz-placeholder

Similar activities

PRE POST TEST BASS MARET 2023

PRE POST TEST BASS MARET 2023

Professional Development

60 Qs

TES TEHNIK PPPK 1

TES TEHNIK PPPK 1

Professional Development

70 Qs

3.MODÜL DEĞERLENDİRME ÇALIŞMASI

3.MODÜL DEĞERLENDİRME ÇALIŞMASI

Professional Development

60 Qs

UP PPG PJOK 2021

UP PPG PJOK 2021

Professional Development

70 Qs

TRY OUT PPPK

TRY OUT PPPK

Professional Development

65 Qs

Leadership: Final Exam Review

Leadership: Final Exam Review

Professional Development

70 Qs

OSI Layer

OSI Layer

University - Professional Development

65 Qs

CIS Microsoft Excel (Review)

CIS Microsoft Excel (Review)

9th Grade - Professional Development

62 Qs

PMP 6th Edition

PMP 6th Edition

Assessment

Quiz

Professional Development

Professional Development

Practice Problem

Medium

Created by

Denera ADVS)

Used 13+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

65 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

An accepted deadline for a project approaches. However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request. What should the change request authorize?

Additional resources using the contingency fund

Escalation approval to use contingency funding

Team overtime to meet schedule

Corrective action based on causes

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

What is meant by RACI?

Responsible, Accountable, Confirm, Inform

Recommended, Accountable, Consulted, Inform

Responsible, Accountant, Consulted, Inform

Responsible, Accountable, Consulted, Inform

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Which of the following statement is true about a Program?

A Program is a group of related projects

A Program is group of unrelated projects

A Program is a part of a big project

None of above

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Assuming that the ends of a range of estimates are +/- 3 sigma from the mean, which of the following range estimates involves the LEAST risk?

30 days, plus or minus 5 days

22 – 30 days

Optimistic = 26 days, most likely = 30 days, pessimistic = 33 days

Mean of 28 days

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

If a risk has a 20 percent chance of happening in a given month, and the project is expected to last five months, what is the probability that the risk event will occur during the fourth month of the project?

Less than 1 percent

60 percent

20 percent

80 percent

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A project has a 60% chance of a $100,000 profit and a 40 percent of a US $100,000 loss. The Expected Monetary Value for the project is:

$40,000 loss

$60,000 loss

$20,000 profit

$100,000 profit

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

During a bidder conference, you see that one bidder is your close friend. What should your next step be?

You will pass some confidential info to him

You will disclose this relationship to your management

You will resign immediately from the bidding process

You will try not to give the contract to him to prove your integrity

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?