1.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
What is recommended size for The Development Team (within the Scrum Team)?
9
Minimal 7
7 +/- 2
2.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
Who should know the most about the process toward a business objective or a release, an be able to explain the alternatives most clearly?
The Scrum Master
The Product Owner
The Development Team
The Project Manager
3.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
When the Sprint is over?
When all Product Backlog items meet their definition of done
When the time-box expires
When all the tasks are completed
When the product Owner says it is completed
4.
MULTIPLE SELECT QUESTION
3 mins • 1 pt
What questions should be answered in the stand-up meeting?
What will I do today?
What did I do yesterday?
Do I see any impediment?
What worked well?
What could be improved?
5.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
What happens during Sprint 0?
Overall planning, base system architecture, base design, version control and continuous integration setup.
Establish base system architecture and design, install version control and continuous integration setup.
Base system architecture and design.
There is no such thing as Sprint 0.
Requirements gathering, version control setup, and continuous integration setup.
6.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
The time-box for a Daily Scrum is?
15 minutes for a 4 week sprint. For shorter Sprints it is usually shorter.
Two minutes per person.
4 hours.
15 minutes.
7.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
Who has the authority to cancel a Sprint?
Product Owner
Scrum Master
Development Team
All roles togethe
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?