
Project Management 6(B)

Quiz
•
Other
•
University
•
Medium

El Awad Osman
Used 31+ times
FREE Resource
23 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
In rolling wave planning:
Focus is maintained on long-term objectives, allowing near-term objectives to be rolled out as part of the ongoing wave of activities.
The work to be accomplished in the near term is planned in detail, whereas the work in the future is planned at a higher level.
The work far in the future is planned in detail for work packages that are at a low level of the WBS.
A wave of detailed activities is planned during strategic planning to ensure that WBS deliverables and project milestones are achieved.
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The precedence diagramming method (PDM) is:
A technique in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
A method that uses a probabilistic approach to scheduling project activities.
A time-phased graphical representation of the arrow diagramming method (ADM), and shows durations of project activities as well as their dependencies.
More accurate than the critical path method for scheduling when there are uncertainties about the durations of project activities.
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The duration of the activity is affected by all of the following EXCEPT:
The estimated activity resource requirements.
The types of resources assigned to the activity.
The availability of the resources assigned to the activity.
Using the precedence diagramming method (PDM) for scheduling activities instead of using the critical path method (CPM).
4.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
A schedule compression technique used to shorten the schedule duration for the least incremental cost by adding resources is called:
Crashing.
Program evaluation and review technique (PERT).
Precedence diagramming method (PDM).
Fast tracking.
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The “fast tracking” method of schedule compression involves:
The use of industrial engineering techniques to improve productivity, thereby finishing the project earlier than originally planned.
Performing in parallel for at least a portion of their duration activities or phases that are normally done in sequence, which may result in rework and increased risk.
Going on a “mandatory overtime schedule” to complete the project on schedule or earlier if possible.
Assigning “dedicated teams” to critical path activities to achieve project schedule objectives.
6.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
An example of a mandatory dependency is:
A dependency established based on knowledge of best practices within a particular application area.
A dependency established based on some unusual aspect of the project where a specific sequence is desired.
On a construction project, to erect the superstructure only after the foundation has been built.
On a software development project, to start design only after completion and approval of all project requirements.
7.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Inputs to the Define Activities process are:
Schedule management plan, work breakdown structure, project schedule, and network diagram.
Project schedule, resource estimates, progress reports, and change requests.
Scope management plan, project network diagram, constraints, and assumptions.
Schedule management plan, scope baseline, enterprise environmental factors, and organizational process assets.
Create a free account and access millions of resources
Similar Resources on Wayground
19 questions
Project Management Quiz

Quiz
•
University
20 questions
POM: Permit System

Quiz
•
10th Grade - Professi...
18 questions
Kuis Perancangan Produk

Quiz
•
University
20 questions
HOC2013 - Meeting practice

Quiz
•
University
20 questions
Autism

Quiz
•
9th Grade - University
20 questions
Unit - 4

Quiz
•
University
22 questions
Project Quality Managment

Quiz
•
11th Grade - Professi...
19 questions
Quiz 3 - Project Management

Quiz
•
University
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade