1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Resources are adequate, but demand varies widely over the life of the project. Delaying noncritical activities to lower peak demand on resources is known as resource

Shifting

Effectiveness

Manipulating

Smoothing

Allocation

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

If resources are not adequate to meet peak demands, the resulting reschedule is termed

Resource-constrained scheduling

Time -constrained scheduling

Mandatory leveling

Project resource adjustment

Allocation

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is NOT a potential consequence of failing to identify limited resources before project implementation?

Activity delays

Project delays

Difficulty in taking quick corrective action

Increase costs

Scope creep

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

When developing a new software package, logically, the software must be designed before the code is written, and the code must be written before it is tested. These activities are dependent on each other by___constraints.

Physical

Technical

Resource

Schedule

Time

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

When considering the sequence and timing of activities, which of the following is NOT one of the types of project network constraints?

Physical

Technical

Resource

Time

All of these are types of constraints that could impact structure of the project network

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Sam, the project engineer, has been scheduled to run the product system test at the same time he is to build a marketing prototype. This is an example of what type of resource constraint?

Physical

Technical

People

Equipment

Time

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test. This is an example of a constraint that could impact the sequence and timing of activities in a project network. What type of constraint is it?

Physical

Technical

Resource

Scheduling

Time

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?