1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Resources are adequate, but demand varies widely over the life of the project. Delaying noncritical activities to lower peak demand on resources is known as resource
Shifting
Effectiveness
Manipulating
Smoothing
Allocation
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
If resources are not adequate to meet peak demands, the resulting reschedule is termed
Resource-constrained scheduling
Time -constrained scheduling
Mandatory leveling
Project resource adjustment
Allocation
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following is NOT a potential consequence of failing to identify limited resources before project implementation?
Activity delays
Project delays
Difficulty in taking quick corrective action
Increase costs
Scope creep
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
When developing a new software package, logically, the software must be designed before the code is written, and the code must be written before it is tested. These activities are dependent on each other by___constraints.
Physical
Technical
Resource
Schedule
Time
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
When considering the sequence and timing of activities, which of the following is NOT one of the types of project network constraints?
Physical
Technical
Resource
Time
All of these are types of constraints that could impact structure of the project network
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Sam, the project engineer, has been scheduled to run the product system test at the same time he is to build a marketing prototype. This is an example of what type of resource constraint?
Physical
Technical
People
Equipment
Time
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test. This is an example of a constraint that could impact the sequence and timing of activities in a project network. What type of constraint is it?
Physical
Technical
Resource
Scheduling
Time
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
54 questions
Analyzing Line Graphs & Tables
Quiz
•
4th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade