15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
What office is responsible for zoning of their respective jurisdictions and final land use and zoning planes to be submitted to HLURB (Housing and Land Use Regulatory Board) for approval?
Provincial Planning Development Office (PPDO)
City Planning Development Office (CPDO)
Municipal Planning and Development Office (MPDO)
All of the above
2.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
Ideal Capacity of a road is:
1800 vehicles/hr
2000 vehicles/hr
1400 vehicles/hr
1200 vehicles/hr
3.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
The required length of the turnout shall be determined considering a length of _____ meters for each bus.
16.0
15.5
15.0
14.5
4.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
The length of superelevation development from the normal cross slope to the zro cross slope point on the tangent is known as:
tangent runoff
tangent runout
super elevation runout
super elevation runoff
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Criteria used for the establishment of sag vertical curves:
I. Headlight sight distance
II. Passenger comfort
III. Drainage control
IV. General appearance
V. Velocity of cars passing thru the curve
I, II, IV and V only
I, II, III and IV only
II, IV and V only
All of the above
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
They are essential part of any road that is not on fill and must be incorporated into the road cross-section. These are designed to accommodate the expected rainfall but can often be hazardous to vehicles that run off the road.
transverse drainage ditches
shoulder
drop curve and gutters
longitudinal drainage ditches
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The most important criteria to consider to avoid safety hazards created by the drainage ditches is the actual reconnaissance survey during wet whether to identify the natural run-out locations. Slopes on the side nearest the road should not be steeper than _____ and preferable flatter as this will minimize accident severity. The slope farthest from the road may be as steep as the ground will permit.
4:1
3:1
2:1
1.5:1
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?