Project Communications Management

Project Communications Management

Professional Development

15 Qs

quiz-placeholder

Similar activities

Anime 99

Anime 99

9th Grade - Professional Development

13 Qs

Customer Service Refresher Program

Customer Service Refresher Program

Professional Development

11 Qs

Post Test Penyusunan LK 2022

Post Test Penyusunan LK 2022

Professional Development

10 Qs

Quiz 3

Quiz 3

Professional Development

10 Qs

DMS REMSCAR QUIZ

DMS REMSCAR QUIZ

Professional Development

15 Qs

How Well Do You Know Glenn?

How Well Do You Know Glenn?

Professional Development

10 Qs

7B.2 (Part 2)

7B.2 (Part 2)

Professional Development

20 Qs

Selling Skills

Selling Skills

Professional Development

15 Qs

Project Communications Management

Project Communications Management

Assessment

Quiz

Other

Professional Development

Hard

Created by

Natalia Faculo

Used 62+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

A project manager has a problem with a team member's performance. What is BEST form of communication for addressing this problem?

Formal written communication

Formal verbal communication

Informal written communication

Informal verbal communication

2.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

Formal written correspondence with the customer is required when:

Defects are detected.

The customer requests additional work not covered under contract.

The project has a schedule slippage that includes changes to the critical path.

The project has cost overruns.

3.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

A large, one-year telecommunications project is about halfway done when you take the place of the previous project manager. The project involves three different sellers and a project team of 30 people. You would like to see the project's communications requirements and what technology is being used to aid in project communications. Where will you find this information?

The stakeholder management plan

The information distribution plan

The bar chart

The communications management plan

4.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

Communication is key to the success of a project. As the project manager, you had three stakeholders with whom you needed to communicate. Therefore, you had six channels of communication. A new stakeholder has been added with whom you also need to communicate. How many communication channels do you have now?

7

10

12

16

5.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

A project manager has a project team consisting of people in four countries. The project is very important to the company, and the project manager is concerned about its success. The length of the project schedule is acceptable. What type of communication should he use?

Informal verbal communication

Formal written communication

Formal verbal communication

Informal written communication

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You have just been assigned as project manager for a large manufacturing project. This one-year project is about halfway done. It involves 5 different sellers and 20 members of your company

on the project team. You want to quickly review where the project now stands. Which of the following reports would be the MOST helpful in finding such information?

Work status

Progress

Forecast

Communications

7.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

A project manager overhears a conversation between two stakeholders who are discussing how unhappy they are with the impacts of the project on their own departments. Stakeholder A asks if the project is on time, and stakeholder B replies that the SPI is 1.05. Stakeholder A asks if the project manager for the project knows of stakeholder B's concern. Stakeholder B responds that he is not sure. What is the BEST thing for the project manager to do?

Make sure the stakeholders see that the project manager overheard. Then ask them to direct any questions to the project manager in writing.

Make a presentation to all the stakeholders regarding the status of the project.

Send both stakeholders a copy of the issue log and ask for additional comments.

Arrange a meeting with both stakeholders to allow them to voice any concerns they may have.

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?