Cavity Wall Construction
Authored by Peter Roberts
Other
2nd Grade
Used 193+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
What is the collective term given to all work carried out above ground level?
Substructure
Superstructure
Above Datum
Walling
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
What document is issued in conjunction with a plan or working drawing and provides written information about the work to be carried out?
COSHH statement
Risk assessment
Specification
Time sheet
3.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
What would be placed between the two leaves of blockwork in footings before backfilling takes place?
Insulation
Lean mix concrete
Mortar
It is left hollow
4.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Masonry cement should not be used in substructure walling because:
It produces a mortar that is too light in colour
It contains a plasticiser that weakens the mortar
It is too expensive
The curing time is too long
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
A strip foundation for a 300mm cavity wall is usually excavated to a width of:
450mm
600mm
750mm
900mm
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
What is the minimum distance a damp proof course should be positioned above ground level?
150mm
300mm
450mm
600mm
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
The three classifications of damp proof course are:
Flexible, semi-flexible, rigid
Brick, slate, plastic
Flexible, semi-rigid, rigid
horizontal, vertical, diagonal
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?