
Construction Management
Quiz
•
•
Medium
Madeleine Sara
Used 2+ times
FREE Resource
Enhance your content in a minute
20 questions
Show all answers
1.
MULTIPLE SELECT QUESTION
2 mins • 1 pt
When a change to the work is required and the GC ask you how to proceed, how do you manage the request as a PM? (Select all that apply)
Direct GC to the AOR to confirm the change is valid
Ask GC to submit a PCO
Ensure that you know why the change is required
Ask the GC to proceed so you avoid delay
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
To avoid having a schedule delay, the GC offers to proceed with a change while you are finalizing paperwork, what would be your next action?
Call the AOR and ask for his/her verbal approval
Call/ email Jason and ask for his verbal approval
Inform GC that proceeding will be on his/her risk
Stop Work
3.
MULTIPLE SELECT QUESTION
2 mins • 1 pt
What do you review when you receive a PCO? (Select all that apply)
Labor burden and subs markups
AOR recommendations for approval
GC summary and AOR Letter
Material quantities and subs qualifications
4.
MULTIPLE SELECT QUESTION
2 mins • 1 pt
How do you consider an unforeseen condition change request package is complete prior to submitting to EPISD? (Select all that apply)
Subs material, equipment, labor and labor burden are provided
Architect signed off the package, GC letter of recommendations, and PCO form
Owner Initiated Change form
Jacobs recommendations letter and CEA when applicable
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Do you negotiate the cost of the change directly with the GC?
Yes, with the GC
Not with the GC, with the subs
AE should validate if the cost is reasonable
Yes, with the suppliers
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Do you approve minor changes that don’t impact time or cost?
Yes, if change is minor and don't impact cost and time
No, AOR should review and approve
GC can proceed and no need for approval
EPISD approves minor changes that don't impact cost and time
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
How do categorize the construction changes?
Unforeseen, owner change, errors and omission and Jacobs request change
Unforeseen, owner change, errors and omission , and AHJ
All the above
Non of the above
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
17 questions
SOAL CONGRATULATION kelas9
Quiz
•
9th Grade
20 questions
Teaching Strategy
Quiz
•
Professional Development
15 questions
Pop Science: DNA
Quiz
•
8th - 12th Grade
15 questions
Bataan History
Quiz
•
7th - 10th Grade
20 questions
Perfect Continuous (Present 'n Past)
Quiz
•
12th Grade
20 questions
FICTION & NON FICTION 18-2-2021
Quiz
•
1st Grade
20 questions
Per MidTerm1/23 M.2
Quiz
•
6th - 8th Grade
15 questions
TALKSHOW TIẾNG ANH SAY HI - IUH
Quiz
•
University
Popular Resources on Wayground
8 questions
2 Step Word Problems
Quiz
•
KG - University
20 questions
Comparing Fractions
Quiz
•
4th Grade
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
Latin Bases claus(clois,clos, clud, clus) and ped
Quiz
•
6th - 8th Grade
22 questions
fractions
Quiz
•
3rd Grade
7 questions
The Story of Books
Quiz
•
6th - 8th Grade
