Construction Management
Quiz
•
•
Medium
Madeleine Sara
Used 2+ times
FREE Resource
Enhance your content in a minute
20 questions
Show all answers
1.
MULTIPLE SELECT QUESTION
2 mins • 1 pt
When a change to the work is required and the GC ask you how to proceed, how do you manage the request as a PM? (Select all that apply)
Direct GC to the AOR to confirm the change is valid
Ask GC to submit a PCO
Ensure that you know why the change is required
Ask the GC to proceed so you avoid delay
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
To avoid having a schedule delay, the GC offers to proceed with a change while you are finalizing paperwork, what would be your next action?
Call the AOR and ask for his/her verbal approval
Call/ email Jason and ask for his verbal approval
Inform GC that proceeding will be on his/her risk
Stop Work
3.
MULTIPLE SELECT QUESTION
2 mins • 1 pt
What do you review when you receive a PCO? (Select all that apply)
Labor burden and subs markups
AOR recommendations for approval
GC summary and AOR Letter
Material quantities and subs qualifications
4.
MULTIPLE SELECT QUESTION
2 mins • 1 pt
How do you consider an unforeseen condition change request package is complete prior to submitting to EPISD? (Select all that apply)
Subs material, equipment, labor and labor burden are provided
Architect signed off the package, GC letter of recommendations, and PCO form
Owner Initiated Change form
Jacobs recommendations letter and CEA when applicable
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Do you negotiate the cost of the change directly with the GC?
Yes, with the GC
Not with the GC, with the subs
AE should validate if the cost is reasonable
Yes, with the suppliers
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Do you approve minor changes that don’t impact time or cost?
Yes, if change is minor and don't impact cost and time
No, AOR should review and approve
GC can proceed and no need for approval
EPISD approves minor changes that don't impact cost and time
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
How do categorize the construction changes?
Unforeseen, owner change, errors and omission and Jacobs request change
Unforeseen, owner change, errors and omission , and AHJ
All the above
Non of the above
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
15 questions
E commerce
Quiz
•
KG
20 questions
Gr 5 - Term 3 - Mock Quiz 4
Quiz
•
5th Grade
20 questions
Food Production System
Quiz
•
University
20 questions
Phonology ai - oa, Let´s plant a tree
Quiz
•
2nd Grade
20 questions
Active Planet - Science and Technology
Quiz
•
2nd - 3rd Grade
19 questions
Sentences and phrases
Quiz
•
5th Grade
15 questions
Quiz 1-15
Quiz
•
9th - 12th Grade
15 questions
Beating Lockdown
Quiz
•
3rd Grade
Popular Resources on Wayground
5 questions
This is not a...winter edition (Drawing game)
Quiz
•
1st - 5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
Identify Iconic Christmas Movie Scenes
Interactive video
•
6th - 10th Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
11 questions
How well do you know your Christmas Characters?
Lesson
•
3rd Grade
14 questions
Christmas Trivia
Quiz
•
5th Grade
20 questions
How the Grinch Stole Christmas
Quiz
•
5th Grade