Activity Graphs

Activity Graphs

12th Grade

10 Qs

quiz-placeholder

Similar activities

CC Activities

CC Activities

7th - 12th Grade

10 Qs

NGPF Taxes (1.1 & 1.2)

NGPF Taxes (1.1 & 1.2)

9th - 12th Grade

15 Qs

Minecraft Noob Quiz

Minecraft Noob Quiz

1st - 12th Grade

12 Qs

National Employment Standards

National Employment Standards

7th - 12th Grade

13 Qs

Positive or normative?

Positive or normative?

11th - 12th Grade

11 Qs

HS Graduation Requirements

HS Graduation Requirements

8th - 12th Grade

11 Qs

8.1 & 8.2 Single-Payment Loans & Installment Loans

8.1 & 8.2 Single-Payment Loans & Installment Loans

11th - 12th Grade

12 Qs

PF 9-3 Lesson

PF 9-3 Lesson

9th - 12th Grade

8 Qs

Activity Graphs

Activity Graphs

Assessment

Quiz

Other

12th Grade

Hard

Created by

Carol-Ann Wiley

Used 6+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Media Image

What is the minimum number of walks needed?

2

3

4

5

2.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Media Image

Allie's bridesmaids are throwing her a bridal shower in a month, and they have several tasks to complete beforehand. The tasks, times (in days) and prerequisites are organized in the chart above. Will they finish in time, if the month is 30 days long?

Yes, and they will have 4 days to spare.

No, they will be 4 days late.

Yes, they will be exactly on time.

Yes, and they will have 17 days to spare.

3.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Media Image

Allie's bridesmaids are throwing her a bridal shower in a month, and they have several tasks to complete beforehand. The tasks, times (in days) and prerequisites are organized in the chart above. How long can you delay task D?

7 days

13 days

6 days

4 days

4.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Media Image

Jolene is starting school at UGA next year and wants to become a Physical Therapist. Her college Advisor has told her she needs to take the following semester courses in order to be admitted into her major.


What’s the minimum amount of time it would take Jolene to be admitted into her major?

7 semesters

4 semesters

3 semesters

5 semesters

5.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Media Image

Determine the minimum time required to complete all the activities shown in the graph.

7

8

9

10

6.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Media Image

Which activities are critical activities?

A, C, and E

A, D, and E

A, D, and F

B, D, and E

B, D, and F

7.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Media Image

How long could Activity F be delayed without affecting the overall completion time?

it cannot be delayed

1 hour

2 hours

3 hours

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?