1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is Phase to Phase Clearance in 11KV Line
280 mm
2600 mm
2750 mm
None
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is Ground Clearance in 11KV Line
280 mm
140 mm
2750 mm
None
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is Electrical Clearance?
Shortest distance in air between two non conductive parts
Shortest distance in air between two conductive parts / conductive part & earth.
Shortest distance in air between conductive parts & non conductive part
None
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following is not the Standards / Statutory norms for clearances :
IEC-60071
IS-10118
IE Rule
IS-10001
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which is not the Physical factors of Site Selection in Sub-station Engineering:-
Topography
Geological
Aeronautics
Geography
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which is not the Infrastructural factors of Site Selection in Sub-station Engineering:-
Easy access
Amenities availability
Reliable power and water supply
Pollution
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which is not the Social & Environmental aspects of Site Selection in Sub-station Engineering:-
Government or private land
Forest encroachment
Landscaping
Pollution
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?