Topic 5 - DPB3013

Topic 5 - DPB3013

University - Professional Development

12 Qs

quiz-placeholder

Similar activities

rubiks cube quiz

rubiks cube quiz

KG - Professional Development

13 Qs

Basic Nutrition

Basic Nutrition

University

10 Qs

RAPAT TELECONFERENCE

RAPAT TELECONFERENCE

12th Grade - University

10 Qs

Food Safety

Food Safety

University - Professional Development

10 Qs

Post-test Epidemiology - Study design

Post-test Epidemiology - Study design

University

10 Qs

KUIS 5,6,7 PEMASARAN FARMASI

KUIS 5,6,7 PEMASARAN FARMASI

University

10 Qs

SERA Day 2022

SERA Day 2022

Professional Development

17 Qs

BCA - Leading Self

BCA - Leading Self

Professional Development

10 Qs

Topic 5 - DPB3013

Topic 5 - DPB3013

Assessment

Quiz

Other

University - Professional Development

Hard

Created by

Fairuzzy Sa'aet

FREE Resource

AI

Enhance your content

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

12 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

There are several principles that determine the effectiveness of a control process. Which of the statements below is the principle of control?
Set the standard
Take corrective action
Focus on important factors
Compare the actual performance with the standards

2.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

If a manager is evaluating the quality of the company’s product by examining complaint forms submitted by customers, then he/she is using which of the following types of control?
Concurrent control
Feedback control
Feed forward control
Yes-no control

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

The schedule of the whole project is created by setting the starting time and the completion time for each activity in the project. This technique is referred to
Milestones Budget
Gantt Chart
Statistical Data
Balance sheet

4.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

1.Managers who conduct_______________control are usually involves in making policies, procedures and rules to eliminate any undesired behaviours.
Feedforward
Concurrent
Feedback
Yes/No

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Managers select a date to accomplish a certain activity, decision or events and show the date on the chart’s line. This control technique known as____________.
PERT
Statistical data
Gantt Chart
Milestone

6.

MULTIPLE SELECT QUESTION

20 sec • 1 pt

There are four steps in the control process. Identify the correct sequence in the controlling process.
Measure the actual performance
Compare the actual performance with the standards
Set the standards
Take corrective actions

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Identify which of the following are NOT the types of control
Feedforward control
Concurrent control
Contingency control
Feedback control

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?