Topic 5 - DPB3013

Topic 5 - DPB3013

University - Professional Development

12 Qs

quiz-placeholder

Similar activities

INTRO PURCHASE & COST CONTROL

INTRO PURCHASE & COST CONTROL

University

10 Qs

Module 5 Quiz

Module 5 Quiz

University

15 Qs

THC 9 - Management & Leadership in Workplace Diversity Quiz

THC 9 - Management & Leadership in Workplace Diversity Quiz

University

10 Qs

Webinar on Assessment of Learning

Webinar on Assessment of Learning

Professional Development

10 Qs

Leadership and Supervision (Pre-test)

Leadership and Supervision (Pre-test)

University - Professional Development

12 Qs

OSCM 306 Ch1 Review

OSCM 306 Ch1 Review

University

10 Qs

HACCP QUIZ MODULE 1

HACCP QUIZ MODULE 1

University

10 Qs

Metrology in Quality Assurance

Metrology in Quality Assurance

University

9 Qs

Topic 5 - DPB3013

Topic 5 - DPB3013

Assessment

Quiz

Other

University - Professional Development

Hard

Created by

Fairuzzy Sa'aet

FREE Resource

12 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

There are several principles that determine the effectiveness of a control process. Which of the statements below is the principle of control?
Set the standard
Take corrective action
Focus on important factors
Compare the actual performance with the standards

2.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

If a manager is evaluating the quality of the company’s product by examining complaint forms submitted by customers, then he/she is using which of the following types of control?
Concurrent control
Feedback control
Feed forward control
Yes-no control

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

The schedule of the whole project is created by setting the starting time and the completion time for each activity in the project. This technique is referred to
Milestones Budget
Gantt Chart
Statistical Data
Balance sheet

4.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

1.Managers who conduct_______________control are usually involves in making policies, procedures and rules to eliminate any undesired behaviours.
Feedforward
Concurrent
Feedback
Yes/No

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Managers select a date to accomplish a certain activity, decision or events and show the date on the chart’s line. This control technique known as____________.
PERT
Statistical data
Gantt Chart
Milestone

6.

MULTIPLE SELECT QUESTION

20 sec • 1 pt

There are four steps in the control process. Identify the correct sequence in the controlling process.
Measure the actual performance
Compare the actual performance with the standards
Set the standards
Take corrective actions

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Identify which of the following are NOT the types of control
Feedforward control
Concurrent control
Contingency control
Feedback control

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?