1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
As per PD1096, the building permit of a construction shall expire if work has been abandoned for how long?
120 days
60 days
90 days
150 days
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The flashing green period required for the disabled should be determined based on the walking speed of?
0.60m/s
6m/s
9m/s
0.90m/s
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Minimum ceiling height for habitable rooms with artificial ventilation of a single storey structure.
1.8m
2.1m
2.4m
2.7m
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does FALAR stand for?
Fire Safe and Life Assessing Report
Floor and Lot Area Ratio
Floor to Lot Area Ratio
Fire Satety and Life Assessment Report
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Smoke detectors should be located _____ maximum from fire exit.
2.1m
3.0m
1.7m
3.11m
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Slope of parking building according to BP344
1:12
1:20
1:25
None of the above
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
RA9514. Maximum vertical height of firewalls from roof
0.6m
0.81m
1.0m
1.12m
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?