1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

1. A project manager is informed midway through project planning that she was given inaccurate data

regarding new regulations affecting the required end date of her project. She may need to make a few

adjustments, but she thinks she can still manage the project to complete it before the regulations take

effect. She confirms this by analyzing the sequence of activities with the least amount of scheduling

flexibility. What technique is she using?

A. Critical path method

B. Flowchart

C. Precedence diagramming

D. Work breakdown structure

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

2. A design engineer is helping to ensure that the dependencies within her area of expertise are properly

defined on the project. The design of several deliverables must be complete before manufacturing can

begin. 1his is an example of what type of dependency?

A. Discretionary dependency

B. External dependency

C. Mandatory dependency

D. Scope dependency

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

3. Your sponsor and stakeholders have made it clear they wish to be kept informed on the project status.

There are many aspects of the project on which you will report, and you want to choose the most

appropriate tool to use in each case. Which of the following are generally illustrated better by bar

charts than network diagrams?

A. Logical relationships

B. Critical paths

C. Resource trade-offs

D. Progress or status

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

4. A heuristic is best described as a:

A. Control tool

B. Scheduling method

C. Planning tool

D. Generally accepted rule

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

5. Lag means:

A. The amount of time an activity can be delayed without delaying the project finish date

B. The amount of time an activity can be delayed without delaying the early start date of its successor

C. Waiting time

D. The product of a forward and backward pass

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

6. A project manager is new to the company but has lO years of project management experience. She is

given a medium-sized project and is asked to plan so it is finished as quickly as possible because the

company has a large list of projects to complete in the coming year. She will be given another project

to manage as soon as she has this one baselined. She needs to report on the longest time the project

will take. Which of the following is the best project management tool to use to determine this?

A. Work breakdown structure

B. Network diagram

e. Bar chart

D. Project charter

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

7. Which of the following is correct?

A. The critical path helps prove how long the project will take.

B. There can be only one critical path.

e. The network diagram will change every time the end date changes.

D. A project can never have negative float.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?