SYSTEM DEVELOPMENT CYCLE

SYSTEM DEVELOPMENT CYCLE

11th - 12th Grade

30 Qs

quiz-placeholder

Similar activities

Computer Science Revison Question

Computer Science Revison Question

11th Grade - University

26 Qs

ICT 2019

ICT 2019

1st Grade - University

30 Qs

project management

project management

12th Grade

34 Qs

Project: 3 Producing and Implementing

Project: 3 Producing and Implementing

7th - 12th Grade

25 Qs

ICT revision

ICT revision

10th - 11th Grade

29 Qs

Grade 11 Tuition Assessment 1- Basic Algorithm

Grade 11 Tuition Assessment 1- Basic Algorithm

11th Grade

25 Qs

Nocti Computer Programming Review

Nocti Computer Programming Review

10th - 12th Grade

28 Qs

GAD Review - Design & Prototype

GAD Review - Design & Prototype

9th - 12th Grade

26 Qs

SYSTEM DEVELOPMENT CYCLE

SYSTEM DEVELOPMENT CYCLE

Assessment

Quiz

Computers

11th - 12th Grade

Hard

Created by

Jude jude

Used 24+ times

FREE Resource

30 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

Define SDLC

Set of activities used to build information system

Collection of phases consist a set of activities to build system

Cycle to build information system

2.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

All the activities include in planning except:

review project request

identify project team

conduct feasibility study

allocate resources

3.

MULTIPLE SELECT QUESTION

20 sec • 1 pt

All the activities in planning are:

identify project team

conduct preliminary investigation

convert system

prioritise project request

allocate resources

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Using the waterfall SDM, a prototype can be developed..

During the Design phase.

During the Development phase.

During the Implementation phase.

During the Analysis phase.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who should review the detailed design before it is developed?
The developer. 
The users. 
As many stakeholders as possible. 
The ICT support team. 

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A programmer would be a useful person to employ in which stage?

Planning

Design.

Implementation.

Analysis.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

eXtreme Programming produces short, incremental development cycles

True

False

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?

Discover more resources for Computers