Project schedule management _2

Project schedule management _2

University

9 Qs

quiz-placeholder

Similar activities

Introduction to physical activity

Introduction to physical activity

University

12 Qs

EU415 Ontario Science Curriculum

EU415 Ontario Science Curriculum

University

10 Qs

property management

property management

University

12 Qs

Introduction to Science Skills in STEM Approach on Solar Energy

Introduction to Science Skills in STEM Approach on Solar Energy

University

5 Qs

CP2 Chapter 11

CP2 Chapter 11

University

10 Qs

Active Learning Activity

Active Learning Activity

9th Grade - University

10 Qs

FIWQS Week 12 Quiz

FIWQS Week 12 Quiz

University

13 Qs

Chapter 3: Making IT Right: Managing Goals, Time, and Costs

Chapter 3: Making IT Right: Managing Goals, Time, and Costs

University

10 Qs

Project schedule management _2

Project schedule management _2

Assessment

Quiz

Science

University

Hard

Created by

Trâm Anh

Used 64+ times

FREE Resource

9 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which is the first step of Schedule management process?

Sequence activity

Estimate activity durations

Determine activities

Develop schedule

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which is the second step of Project scheduling process?

Define activity

Estimate activity durations

Plan schedule management

Develop schedule

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Which purpose of this Gantt chart?

Planning

Monitor

Make a decision

Make a choice

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

In this table, which information do we need more to build the schedule management plan up?

Activity list

Duration

Predecessor

CPM

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

In this table, which information do we need to know if we would like to develop the project schedule management?

Activity list

Sequence activity

Duration

Task coding

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Analogous estimating uses:

Decide the total, then divide that total into the tasks or phases

Using data and variables to calculate the total

Use data from similar projects to decide a similar total

Estimate all the individual parts and add them together to get the total

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which activity is in project estimation?

Defining activities

Resource

Develop schedule

Sequencing

8.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

PERT is a technique, used to manage

activities of a project

sequencing

quality

uncertain tasks of a project

9.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Slack time in project management is :

The latest point in time when the schedule activity can begin so as not to delay the project completion date or any constraint.

time a task can be delayed without causing another task to be delayed, or without impacting the overall project completion

The earliest point in time when the schedule activity can begin

The earliest point in time when the schedule activity can complete