20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is the process of obtaining seller responses, selecting a seller and awarding a contract?

Plan procurement management

Conduct Procurements

Control Procurements

Close Procurements

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

All of the following are procurement documents, except

Request for Information

Request for Proposal

Request for Quotation

Request for Tender

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Your team decided to outsource a complex sub-part to an outside vendor. Owing to the complexity of nature of the item and the importance of the unit for the entire project, you decided to call your perspective sellers in a conference where they can have clear understanding of the requirements about the part of product. What is this type of conference is known as?

Prospective seller conference

Seller conference

Bidder conference

Pre-seller conference

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Procurements audit is a tool or technique of the following process

Plan procurements

Conduct procurements

Control procurements

Close procurements

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A contract which involve payments as per the actual costs incurred for completion of work, plus a fee representing seller profit is known as -

Cost-reimbursable

Fixed price

Time and Material

Fixed Price Plus Cost

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You have signed a time and materials contract with your customer for a work of around 18 months. Your team worked efficiently and finished the work in 16 months itself. Now, if you create invoice for only 16 months, profit of the company will decrease. What you should do in such a situation?

Add some additional requirements to elongate the project to 18 months

Raise invoice for 18 months even if you finished the work in 16 months

Inform the customer that project is complete in 16 months and raise invoice for 16 months

Do not inform the customer regarding the completion and wait till 18 months, in parallel start doing the ground work for the next period

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The documents that describe the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services or results?

Procurement statement of work

Procurement plan

Procurement documents

Procurement agenda

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development