
PRINCE 2 - Sample Paper 1 (60Q)
Authored by Yassine Chahraoui
Professional Development, Education, Other
Professional Development
Used 19+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
60 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is the first step in the recommended risk management procedure?
Assess
Identify
Implement
Plan
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which statements about a project's stakeholders are CORRECT?
1. A stakeholder is anyone who thinks they will be affected by a project
2. Stakeholders require equal amounts of engagement by the project management team
3. Stakeholders remain unchanged throughout the project
4. A stakeholder may be internal or external to the corporate organization
1 and 2
2 and 3
3 and 4
1 and 4
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A purpose of the [ ? ] theme is to control any unacceptable deviations from the project's objectives.
Change
Plans
Progress
Risk
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which is a minimum requirement for applying the organization theme?
To define the project assurance role of team managers
To combine roles, where possible, to simplify the organization
To appoint a business change manager as senior user when the project is part of a programme
To define the approach to engaging with stakeholders
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is defined when deciding how to tailor PRINCE2 to suit the project?
When the project's progress will be reviewed
Which of the six tolerance areas will be included
Which primary stakeholder interests will be represented
When the project's outputs will be delivered
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which statement about the 'continued business justification' principle is CORRECT?
The justification for compulsory projects does not need approval
There must be no change to the reasons for a project
A formal business case document is mandatory
The chosen option must provide value for money
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which regular report provides the project board with a summary of stage status?
Lessons report
Product status account
Highlight report
Checkpoint report
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
58 questions
VT5_Promoción de bienes inmuebles
Quiz
•
10th Grade - Professi...
62 questions
FTCE- Media Specialist Test
Quiz
•
Professional Development
58 questions
UK Driving Test
Quiz
•
Professional Development
60 questions
IFCD40 P.P 1
Quiz
•
Professional Development
64 questions
CompTIA Security + : Architecture and Design
Quiz
•
Professional Development
63 questions
DEP Start Guide Test
Quiz
•
12th Grade - Professi...
60 questions
QUESTIONNAIRE 7
Quiz
•
Professional Development
62 questions
miraculous 🐞 ladybug
Quiz
•
KG - Professional Dev...
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
29 questions
Alg. 1 Section 5.1 Coordinate Plane
Quiz
•
9th Grade
22 questions
fractions
Quiz
•
3rd Grade
11 questions
FOREST Effective communication
Lesson
•
KG
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade