What is the first step in the recommended risk management procedure?
PRINCE 2 - Sample Paper 1 (60Q)

Quiz
•
Professional Development, Education, Other
•
Professional Development
•
Medium
Yassine Chahraoui
Used 19+ times
FREE Resource
60 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Assess
Identify
Implement
Plan
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which statements about a project's stakeholders are CORRECT?
1. A stakeholder is anyone who thinks they will be affected by a project
2. Stakeholders require equal amounts of engagement by the project management team
3. Stakeholders remain unchanged throughout the project
4. A stakeholder may be internal or external to the corporate organization
1 and 2
2 and 3
3 and 4
1 and 4
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A purpose of the [ ? ] theme is to control any unacceptable deviations from the project's objectives.
Change
Plans
Progress
Risk
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which is a minimum requirement for applying the organization theme?
To define the project assurance role of team managers
To combine roles, where possible, to simplify the organization
To appoint a business change manager as senior user when the project is part of a programme
To define the approach to engaging with stakeholders
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is defined when deciding how to tailor PRINCE2 to suit the project?
When the project's progress will be reviewed
Which of the six tolerance areas will be included
Which primary stakeholder interests will be represented
When the project's outputs will be delivered
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which statement about the 'continued business justification' principle is CORRECT?
The justification for compulsory projects does not need approval
There must be no change to the reasons for a project
A formal business case document is mandatory
The chosen option must provide value for money
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which regular report provides the project board with a summary of stage status?
Lessons report
Product status account
Highlight report
Checkpoint report
Create a free account and access millions of resources
Similar Resources on Quizizz
56 questions
Đề TM2012 trên istqb.org

Quiz
•
Professional Development
56 questions
FE Chapter 3 quiz

Quiz
•
Professional Development
55 questions
IIMS 2semInternet Fundamentals and Applications Mid term Trial

Quiz
•
Professional Development
65 questions
PMP 6th Edition

Quiz
•
Professional Development
60 questions
Revision-Sample 2

Quiz
•
Professional Development
59 questions
P3G Practice Questions

Quiz
•
Professional Development
64 questions
APS Quiz 2

Quiz
•
Professional Development
60 questions
PMP 380 mock questions - Full mock - part 2

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade