Project Management - Planning
Authored by Rathish Raghupathy
Other
12th Grade
Used 229+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
10 questions
Show all answers
1.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
Which of the following is the second phase in project management ?
Planning
Initiating
Monitoring and controlling
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which among these is termed as the work required to deliver the product?
Product Scope
Project Scope
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is the process of developing a detailed description of the project and product ?
Scope
Project
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project scope focuses on
"What" of the project
"Which" of the project
"How" of the project
"When" of the project
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following stakeholder makes the details of scope in a project ?
Project team
Project Manager
Project Sponsor
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following persons need more information to develop a detailed plan for the project?
Project Stakeholders
Project Team
Project Manager
Project consultant
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What if the project manager provides more information about the project?
It decreases the likelihood of a satisfactory product
It increases the likelihood of a satisfactory product
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?