Time Management in Building Construction

Time Management in Building Construction

University

8 Qs

quiz-placeholder

Similar activities

chapter 7 strategy formulation: corporate strategy

chapter 7 strategy formulation: corporate strategy

1st Grade - Professional Development

10 Qs

Lighting Design Set 1

Lighting Design Set 1

University

10 Qs

Community Involvement VS Cultural Heritage Management

Community Involvement VS Cultural Heritage Management

University

10 Qs

Elevations

Elevations

11th Grade - Professional Development

10 Qs

3D Rigid Body Equilibrium

3D Rigid Body Equilibrium

University

10 Qs

7) Project Management and Filing.

7) Project Management and Filing.

University

10 Qs

QUIZ 2

QUIZ 2

University

10 Qs

Sound Properties & Behaviour

Sound Properties & Behaviour

University - Professional Development

11 Qs

Time Management in Building Construction

Time Management in Building Construction

Assessment

Quiz

Architecture

University

Medium

Created by

ilhamdaniah upi.edu

Used 19+ times

FREE Resource

8 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The construction work for the Brown single family home is due to start ..... week 30.

in

on

at

from

during

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The main contractor, John White, will be on site .... a total of 8 weeks.

in

on

at

for

during

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Their work has to be completed .... 14 September in order to allow enough time for the other trades.

in

on

at

for

during

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The joiner, Williams, is due to start work .... 3 September.

in

on

at

for

during

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Once he has finished the windows, he will be off site .... 17 September.... 29 October.

on - on

from - to

at - at

during - to

during - and

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The companies Frazer and T+P will also suspend their work ... 3 weeks while the plastering and screeding work is being carried out.

in

on

at

for

from

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

It is essential that the screeder finishes ... 9 September in order to allow the screed to dry sufficiently before the oak-strip parquette is being installed.

in

on

at

for

during

8.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The painter will be out ... the end of week 44. However there is a buffer of 5 days for overruns and remedial works.

in

on

at

for

during