Quick Test 2

Quick Test 2

1st Grade

5 Qs

quiz-placeholder

Similar activities

Connectel-Xchange Assessment Nov 1 of 2

Connectel-Xchange Assessment Nov 1 of 2

1st - 5th Grade

10 Qs

all tasks among us

all tasks among us

KG - Professional Development

10 Qs

Objectos de la clase Abrams

Objectos de la clase Abrams

KG - University

10 Qs

PRODUKNOWLEDGE APRIL 2022

PRODUKNOWLEDGE APRIL 2022

1st Grade

10 Qs

Endocrine System Quiz

Endocrine System Quiz

KG - University

10 Qs

minecraft basics

minecraft basics

KG - Professional Development

10 Qs

CrossoverQuiz

CrossoverQuiz

KG - University

10 Qs

Nba

Nba

KG - 12th Grade

10 Qs

Quick Test 2

Quick Test 2

Assessment

Quiz

Other

1st Grade

Easy

Created by

Bich Nguyen

Used 3+ times

FREE Resource

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the Sprint Backlog?

The plan for delivering Product Backlog items

The Product Backlog items selected for this Sprint plus the plan for delivering them

The Product Backlog items selected for this Sprint plus the Team Backlog items

The Product Backlog items selected for this Sprint

2.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

How does the Scrum Master serve the Organization? Select the three most appropriate answers.

Mixing experienced developers and junior specialists across different Development Teams in the organization to speed up Scrum adoption

Working with other Scrum Masters to increase the effectiveness of the application of Scrum in the organization

Planning Scrum implementations within the organization

Leading and coaching the organization in its Scrum adoption

Making sure the key stakeholders are invited on all Scrum Reviews within organization

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

he Development Team should not be interrupted during the Sprint. The Sprint Goal should

remain intact. These are conditions that foster creativity, quality and productivity.

(Which one the following answers is FALSE?)

The Product Owner can help clarify or optimize the Sprint when asked by the Development Team.

The Development Team may work with the Product Owner to remove or add work if it finds it has more or less capacity than it expected.

The Sprint Backlog is fully formulated in the Sprint Planning meeting and does not change during the Sprint.

As a decomposition of the selected Product Backlog Items, the Sprint Backlog changes and may grow as the work emerges

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If an inspector determines that one or more aspects of a process deviate outside acceptable limits, when must an adjustment be made?

As soon as possible to minimize further deviation

The deviations should be discussed at the Daily Scrum and then an adjustment must be made

After Scrum Master approval

After clarifying all the details with the Product Owner

5.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

The Scrum Master does the following regarding the Daily Scrum (select all applicable variants):

If others are present at the Daily Scrum, ensures that they do not disrupt the meeting

Ensures that the Development Team has the meeting

Teaches the Development Team to keep the Daily Scrum within the 15-minute time-box

Is responsible for conducting the Daily Scrum