1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

What should be a project manager do or follow to ensure clear boundaries for project completion?

Scope verification

Completing a scope statement

Risk management plan

Scope definition

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Your project team for a new product development project is determined to produce the most accurate cost estimates possible. As the project manager, which of the following estimation techniques would you recommend the team use to create the most accurate estimate?

Top-down estimating

Bottom-up estimating

Analogous estimating

Parametric estimating

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Under which conditions is the parametric method of estimating most reliable?

When estimating is done at higher level and distributed down to activities

When considerable historical data is taken into account

When expert judgement is used

When estimating is done at activity level and then summed up for the project

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Donald is currently leading his project team in the completion of the implementation phase of a project to upgrade a manufacturing plant with new equipment. Despite his efforts to influence spending decisions, he laments that the project may miss its defined deadline because he does not have control over the allocation and management of his project's budget. In which of the following organizational structures is Donald working?

Functional

Project-oriented

Strong-matrix

PMO

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Your project has a budget of RM 130,000 and is expected to last 10 months, with the work and budget spread evenly across all months. The project is now in month three, the work is on schedule, but you have spent RM 65,000 of the project budget. What is your cost variance?

RM 65,000

RM64,999

RM 39,000

RM 26,000

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

You are the project manager for the JKH Project. You have elected to use parametric estimating in your cost estimating for the project. Which of the following is an example of parametric estimating?

RM 949 per ton

Historical information from a similar project

Estimates built bottom-up based on WBS

Estimates based on top-down budgeting

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

You can purchase pea gravel for your project at RM 437 per metric ton. You need four tons of the pea gravel, so you predict your costs will be RM 1,748. This is an example of which cost-estimating approach?

Top-down

Bottom-up

Analogous

Parametric

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?