
Quiz No-6
Authored by Prof. Gaikwad
English
University
Used 6+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
PERT analysis is based on
Optimistic time
Pessimistic time
Most likely time
All the above.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the option is not a notable challenge while scheduling a project?
Deadlines exist.
Independent activities.
Too many workers may be required.
Costly delay
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The particular task performance in CPM is known
Dummy
Event
Activity
Contract.
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The earliest start time rule
Compares the activities starting time for an activity successor.
Compares the activities end time for an activity predecessor.
Directs when a project can start.
Regulates when a project must begin.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The critical path
Is a path that operates from the starting node to the end node
Is a mixture of all paths.
Is the longest path
Is the shortest path
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Completion of a CPM network diagram activity is commonly known
Connector
Event
Node
All the above.
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Activities A, B, and C are the immediate predecessors for Y activity. If the earliest finish times for the three activities are 12, 15, and 10, then the earliest start time for Y will be
10
15
12
Cannot be determined
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?