TERMINATION OF CONTRACT
Authored by NURUL HISHAMUDIN
Other
University
Used 33+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is termination?
The cancellation of an outsourcing agreement
An argument or disagreement between two people, groups or countries discussion about a subject where there is disagreement
An issue that is the result of a license not meeting a requirement or standard where the cause was reasonably within the license's ability to foresee and correct, and that should have been prevented
Method for assigning responsibility to an organization or an individual for providing design and constructionservices.
2.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
What is the type of contract breaches?
(choose 2 answer)
Insolvency
Minor contract material
Bankruptcy
Major contract material
3.
MULTIPLE SELECT QUESTION
20 sec • 1 pt
What are the causes of contract termination?
( choose 3 answer)
Breach of contract
Convenience
Workers failed to make payment
Insolvency/bankruptcy
4.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
"Situation where nether party has defaulted on the contract but other circumstances have prevented the contract from being performed as originally intended."
From the statement above, which definition does it refers to?
Force majeure
Insolvency
Breach of contract
Frustration
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Once the contract terminated by Employer, all these actions need to be taken by Contractor... EXCEPT
Return the all documents such as drawings to Civil&Structural engineer
Vacate and remove the belongings from the site
Sell the remaining belongings to the employer
Leave the site immediately
6.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
PAM 2006 Contract is a standard contract use for building works in Malaysia.
What is the rights and duties of the Employer and Contractor in Clause 25.4 (d) ?
(choose 2 answer)
The Employer is entitled by himself or to employ others to complete the outstanding works
The Contractor is not entitled to any monies until after completion of the outstanding works by the Employer
The Contractor must vacate the site and remove all equipment and personnel (including his sub-contractor)
The Employer to claim expenses, loss, damages suffered
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the function of interim certificate?
Provide mechanism for the client to make payment to the contractor before the work are complete
Ensure the employer inform of death or his ceasing within 30 days
Suspend the whole uncompleted work for a continuous period pf time
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?