
RitaBook2
Quiz
•
Computers
•
University
•
Medium
Orpheus Telos
Used 4+ times
FREE Resource
Enhance your content in a minute
88 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During project planning, you estimate the time needed for each activity and then total the estimates to create the project estimate. You commit to completing the project by this date. What is wrong with this scenario?
The team did not create the estimate, and estimating takes too long using that method
The team did not create the estimate, and a network diagram was not used
The estimate is too long and should be created by management
The project estimate should be the same as the customer's required completion date.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are a project manager on a $5,000,000 software development project. While working with your project team to develop a network diagram, you notice a series of activities that can be worked in parallel but must finish in a specific sequence. What type of activity sequencing method is required for these activities?
Precedence diagramming method
Arrow diagramming method
Critical path method
Operational diagramming method
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are a project manager on a US $5,000,000 software development project. While working with your project team to develop a network diagram, your data architects suggest that quality could be improved if the data model is approved by senior management before moving on to other design elements. They support this suggestion with an article from a leading software development journal. Which of the following best describes this type of input?
Mandatory external dependency
Discretionary external dependency
External regulatory dependency
Heuristic
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Base on the following, if you needed to shorten the duration of the project, which activity would you try to shorten?
Activity: Start A B C D E F G H I
Preceding Activity: None Start Start Start A B,C C D E F G,H,I
Duration in Weeks: 0 1 2 6 10 1 2 3 9 1 0"
Activity B
Activity D
Activity H
Activity C
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You have a project with the following activities: Activity A takes 40 hours and can start after the project starts.Activity B takes 25 hours and should happen after the project starts. Activity C must happen after activity A and takes 35 hours. Activity D must happen after activities B and C and takes 30 hours. Activity E must take place after activity C and takes 10 hours. Activity F takes place after Activity E and takes 22 hours. Activities F and D are the last activities of the project. Which of the following is true if activity B actually takes 37 hours?
The critical path is 67 hours
The critical path changes to Start, B, D, End
The critical path is Start, A, C, E, F, End.
The critical path increases by 12 hours
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager has received activity duration estimates from his team. Which of the following does he need in order to complete the Develop Schedule process?
Earned value analysis
Schedule change control system
Trend analysis
Reserves
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager is taking over a project from another project manager during project planning. If the new project manager wants to see what the previous project manager planned for managing changes to the schedule, it would be best to look at the:
Communications management plan
Update management plan
Staffing management plan
Schedule management plan
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?
Similar Resources on Wayground
93 questions
IT-турнир
Quiz
•
University
92 questions
A+Core 1 (200-300)#3
Quiz
•
10th Grade - University
90 questions
Phần I
Quiz
•
University
85 questions
ITPC12 Reviewer ch1
Quiz
•
University
87 questions
Final Exam Prep Review
Quiz
•
University
91 questions
Đề 13 E3 HT 23.24
Quiz
•
University
84 questions
CMP128 Java Ch. 11-07-05-04 Exam #2 Study Guide Quiz
Quiz
•
University
90 questions
Com-sci Quiz
Quiz
•
University
Popular Resources on Wayground
20 questions
Halloween Trivia
Quiz
•
6th - 8th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
15 questions
Order of Operations
Quiz
•
5th Grade
20 questions
Halloween
Quiz
•
5th Grade
16 questions
Halloween
Quiz
•
3rd Grade
12 questions
It's The Great Pumpkin Charlie Brown
Quiz
•
1st - 5th Grade
20 questions
Possessive Nouns
Quiz
•
5th Grade
10 questions
Halloween Traditions and Origins
Interactive video
•
5th - 10th Grade
Discover more resources for Computers
10 questions
Halloween Movies Trivia
Quiz
•
5th Grade - University
12 questions
Halloween
Quiz
•
3rd Grade - University
5 questions
Using Context Clues
Interactive video
•
4th Grade - University
20 questions
Definite and Indefinite Articles in Spanish (Avancemos)
Quiz
•
8th Grade - University
7 questions
Force and Motion
Interactive video
•
4th Grade - University
14 questions
Eat Healthy,Be Healty
Quiz
•
4th Grade - University
7 questions
History of Halloween: Pagan or Christian?
Interactive video
•
11th Grade - University
7 questions
Renewable and Nonrenewable Resources
Interactive video
•
4th Grade - University
