1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During project planning, you estimate the time needed for each activity and then total the estimates to create the project estimate. You commit to completing the project by this date. What is wrong with this scenario?
The team did not create the estimate, and estimating takes too long using that method
The team did not create the estimate, and a network diagram was not used
The estimate is too long and should be created by management
The project estimate should be the same as the customer's required completion date.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are a project manager on a $5,000,000 software development project. While working with your project team to develop a network diagram, you notice a series of activities that can be worked in parallel but must finish in a specific sequence. What type of activity sequencing method is required for these activities?
Precedence diagramming method
Arrow diagramming method
Critical path method
Operational diagramming method
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are a project manager on a US $5,000,000 software development project. While working with your project team to develop a network diagram, your data architects suggest that quality could be improved if the data model is approved by senior management before moving on to other design elements. They support this suggestion with an article from a leading software development journal. Which of the following best describes this type of input?
Mandatory external dependency
Discretionary external dependency
External regulatory dependency
Heuristic
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Base on the following, if you needed to shorten the duration of the project, which activity would you try to shorten?
Activity: Start A B C D E F G H I
Preceding Activity: None Start Start Start A B,C C D E F G,H,I
Duration in Weeks: 0 1 2 6 10 1 2 3 9 1 0"
Activity B
Activity D
Activity H
Activity C
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You have a project with the following activities: Activity A takes 40 hours and can start after the project starts.Activity B takes 25 hours and should happen after the project starts. Activity C must happen after activity A and takes 35 hours. Activity D must happen after activities B and C and takes 30 hours. Activity E must take place after activity C and takes 10 hours. Activity F takes place after Activity E and takes 22 hours. Activities F and D are the last activities of the project. Which of the following is true if activity B actually takes 37 hours?
The critical path is 67 hours
The critical path changes to Start, B, D, End
The critical path is Start, A, C, E, F, End.
The critical path increases by 12 hours
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager has received activity duration estimates from his team. Which of the following does he need in order to complete the Develop Schedule process?
Earned value analysis
Schedule change control system
Trend analysis
Reserves
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager is taking over a project from another project manager during project planning. If the new project manager wants to see what the previous project manager planned for managing changes to the schedule, it would be best to look at the:
Communications management plan
Update management plan
Staffing management plan
Schedule management plan
Create a free account and access millions of resources
Similar Resources on Wayground
87 questions
It essentials chapters 1-14

Quiz
•
9th Grade - University
86 questions
Revision_PSPM_MULTIMIDEA

Quiz
•
University
83 questions
ITP 324 - Quiz 1

Quiz
•
University
90 questions
Hardware#1

Quiz
•
University
91 questions
IT 323 Reviewer

Quiz
•
University
89 questions
EA Quiz 3

Quiz
•
University
90 questions
H

Quiz
•
University
88 questions
Project Management Quiz

Quiz
•
University
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade