1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The project sponsor has just signed the project charter. What is the NEXT thing to do?

Begin to complete work packages.

Validate scope.

Start integrated change control.

Start to create management plans.

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The high-level project schedule constraints have just been determined. What project management process group are you in?

Initiating

Planning

Executing

Monitoring and controlling

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The WBS and WBS dictionary are completed. The project team has begun working on identifying risks. The sponsor contacts the project manager, requesting that the responsibility assignment matrix be issued. The project has a budget of US $100,000 and is taking place in three countries using 14 human resources. There is little risk expected for the project, and the project manager has managed many projects similar to this one. What is the NEXT thing to do?

Understand the experience of the sponsor on similar projects.

Create an activity list.

Make sure the project scope is defined.

Complete risk management and issue the responsibility assignment matrix.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager does not have much time to spend on planning before the mandatory start date arrives. He therefore Wants to move through planning as effectively as possible. What advice would you offer?

Make sure you have a signed project charter and then start the WBS.

Create an activity list before creating a network diagram.

Document all the known risks before you document the high-level assumptions.

Finalize the quality management plan before you determine quality metrics.

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The BEST time to assign a project manager to a project is during:

Integration.

Project selection.

Initiating.

Planning.

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager gets a call from a team member notifying him that there is a variance betweenthe speed of a system on the project and the desired or planned speed. The project manager is surprised because that performance measurement was not identified in planning. If the project manager then evaluates whether the variance warrants a response, he is in which part of the project management process?

Initiating

Executing

Monitoring and controlling

Closing

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A team member notifies the project manager that the activities comprising a work package are no longer appropriate. It would be BEST for the project manager to be in what part of the project management process?

Corrective action

Integrated change control

Monitoring and controlling

Project closing

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?