2391-50 Inspection and Testing

Quiz
•
Other
•
1st - 12th Grade
•
Hard

Chris Falet
Used 40+ times
FREE Resource
40 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
1 What is the main purpose of an Initial Verification?
A. To complete the testing and issue an Electrical Installation Certificate.
B. To make a judgement that the installation is safe for continued use.
C. To confirm an installation is safe to be put into service.
D. To ensure all testing has been carried out.
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
2 What situation requires the issuing of a Minor Electrical Installation Works Certificate?
A. An additional lighting circuit has been installed.
B. Changing a consumer unit and protective devices.
C. Upgrading the cable and circuit breaker for a shower circuit.
D. Additional socket-outlets added to an existing ring final circuit.
3.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
3 Which statutory document contains specific information relevant to Initial Verification?
A. The Electricity at Work Regulations.
B. Health and Safety guidance GS38.
C. The Health and Safety at Work Act.
D. BS 7671, Requirements for Electrical Installations.
4.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
4 What is the minimum voltage which requires the test leads and probes to comply with GS38?
A. 25 V AC.
B. 50 V AC.
C. 120 V AC.
D. 150 V AC.
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
5 How many voltage measurements are required to confirm that a three-phase four-wire installation is safely isolated?
A. 3
B. 6
C. 9
D. 10
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
6 What precaution is required before carrying out a test of external earth fault loop impedance (Ze) so as to avoid danger to users of an installation?
A. Lock off the supply.
B. Use insulated screwdrivers.
C. Warn the occupier of the premises.
D. Disconnect the main protective bonding conductors.
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
7 Why does BS 7671 require inspection to be carried out before testing?
A. To confirm the installers have installed as per the job specification.
B. To confirm all the equipment is connected to the installation will work.
C. To confirm the installation is complete and it is safe to commence testing.
D. To confirm the Earthing Conductor is connected and it is safe to commence testing.
Create a free account and access millions of resources
Similar Resources on Wayground
43 questions
Electric Circuits, Conductors, and Insulators

Quiz
•
5th Grade
40 questions
Electricity test

Quiz
•
6th Grade
45 questions
ARDUINO Lesson 2 Quiz

Quiz
•
10th Grade
45 questions
Technology - Quiz 2

Quiz
•
12th Grade
45 questions
Electrical Engineering Quiz

Quiz
•
12th Grade
36 questions
Electrical installations technology

Quiz
•
11th Grade
40 questions
Electrical Grounding and Its Types

Quiz
•
7th Grade
40 questions
Robotics 11 - Bridging Examination

Quiz
•
11th Grade
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
Discover more resources for Other
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade