Chapter 04 - Integration Management
Quiz
•
Special Education
•
University
•
Medium
Suci Miranda
Used 18+ times
FREE Resource
20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
2 mins • 5 pts
Joe has been managing a heavy equipment manufacturing project. Even though all requirements were collected in detail from different stakeholders in the early stages of the project, more requirements have been introduced in the later stages of planning, rsulting in change request. What should be the main objective of the project manager during the change request process?
2.
MULTIPLE CHOICE QUESTION
3 mins • 5 pts
Matthew is called in to lead a prestigious project for his organization. During the course of the project, there are numerous issues about which the top managers raise concerns. But Matthew does not pay attention to the open issues and goes about managing the project the way he feels it is right. At the end of the project, he does manage to succeed in meeting the project objectives but there is an underlying concern about the long term effectiveness of his leadership style. He performs all of the activities necessary for project closure and asks the stakeholders for a formal sign-off on the project. However, the stakeholders are not willing to sign off on the project. What should Matthew do in this scenario?
3.
MULTIPLE CHOICE QUESTION
3 mins • 5 pts
You are the project manager in a manufacturing firm building a custom motorcycle for a client. The client has specified that he loves to go for long rides and would like to have a large capacity tank on the motorcycle. He also specified a luggage holder which would be handy for long trips. You have gathered all the requirements but have not documented the criteria for acceptance. The motorcycle is almost complete and you have asked the client to have a look at the finished product. While verifying the scope and quality of deliverables the client indicates that the tank is not big enough. He also specifies that the luggage holder is bigger that he was expecting. You have agreed to redo the work and deliver but there is a substantial cost involved to get the work redone. Which of the following, if performed, could have helped in reducing the risk of rework at the last moment on this project?
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following is not an input to the Develop Project Charter Process?
5.
MULTIPLE CHOICE QUESTION
2 mins • 5 pts
Ruth has prepared the project statement of work and the contract for her project. However she has not yet prepared the business case. The project sponsor is anxiously waiting to receive and sign the project charter so that the project can be started as soon as possible. Because of this need for speed, Ruth is considering to immediately start developing the project charter. If Ruth jumps directly to creating the project charter, what would she have done wrong?
6.
MULTIPLE CHOICE QUESTION
2 mins • 5 pts
Your agency is running four different projects simultaneously using a pool of shared resources across all projects. The project managers are always trying to get resources for their own projects, which is causing a lot of resource problems. Who is responsible for managing shared resources across all projects?
7.
MULTIPLE CHOICE QUESTION
5 mins • 5 pts
You have been assigned to manage the development of an organizations first website. The site will be highly complex and interactive and neither you and the project team, nor the client has much experience with website development. The timeline is extremely aggressive. Any delay will be costly for both your firm and the client. Your project sponsor approaches you and asks you to quickly develop the Project Charter within a day and start working on the Scope Statement immediately after he approves the Project Charter. What should be your response?
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?
Similar Resources on Wayground
20 questions
Employment Preparation-Unit One Review
Quiz
•
4th Grade - Professio...
20 questions
kepalangmerahan
Quiz
•
KG - Professional Dev...
20 questions
Mr beast quiz
Quiz
•
KG - Professional Dev...
15 questions
Prof S, R. - Cell activity / quiz
Quiz
•
University
21 questions
Municipal Solid Waste Management
Quiz
•
University
15 questions
CURRENT AFFAIRS
Quiz
•
KG - Professional Dev...
20 questions
Chapter 03 - Management Process
Quiz
•
University
20 questions
Phonetic Substitution and Phonetic Manipulation Assessment
Quiz
•
6th Grade - University
Popular Resources on Wayground
20 questions
Halloween Trivia
Quiz
•
6th - 8th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
15 questions
Order of Operations
Quiz
•
5th Grade
20 questions
Halloween
Quiz
•
5th Grade
16 questions
Halloween
Quiz
•
3rd Grade
12 questions
It's The Great Pumpkin Charlie Brown
Quiz
•
1st - 5th Grade
20 questions
Possessive Nouns
Quiz
•
5th Grade
10 questions
Halloween Traditions and Origins
Interactive video
•
5th - 10th Grade
Discover more resources for Special Education
10 questions
Halloween Movies Trivia
Quiz
•
5th Grade - University
12 questions
Halloween
Quiz
•
3rd Grade - University
5 questions
Using Context Clues
Interactive video
•
4th Grade - University
20 questions
Definite and Indefinite Articles in Spanish (Avancemos)
Quiz
•
8th Grade - University
7 questions
Force and Motion
Interactive video
•
4th Grade - University
14 questions
Eat Healthy,Be Healty
Quiz
•
4th Grade - University
7 questions
History of Halloween: Pagan or Christian?
Interactive video
•
11th Grade - University
7 questions
Renewable and Nonrenewable Resources
Interactive video
•
4th Grade - University