Which of the following is not a tool or technique for collecting requirements?
brainstorming
preparing a gantt chart
conducting interviews
facilitating focus group
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The role of the project manager includes
leading the team that is responsible for achieving the project objectives.
leading the human resources department to meet the labor ratio requirements.
leading the functional managers towards reaching the strategic objectives.
all of the above
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is not an input to developing the project charter?
business care
risk management plan
project statement of work
enterprise environmental factors
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is not a project constraint?
schedule
quality
stakeholder
budget
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An approved change request
is an output of the Perform Integrated Change Control process.
can modify the project budget and schedule.
may be a corrective action, a preventative action, or a defect repair.
all of these
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
To create the Work Breakdown Structure, a project manager
lumps together the related work activities to better manage them.
subdivides project deliverables and project work into smaller, more manageable components.
subdivides the project budget to fit each project phase.
lumps together the related project deliverables into larger project phases.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which answer includes the five project management process groups?
initiating process group, performing process group, executing process group, monitoring and controlling process group, and the closing process group
investigating process group, planning process group, estimating process group, monitoring and controlling process group, and the closing process group
initiating process group, planning process group, executing process group, monitoring and controlling process group, and the closing process group
investigating process group, planning process group, deciding process group, monitoring and controlling process group, and the closing process group
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?