1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is not a tool or technique for collecting requirements?

brainstorming

preparing a gantt chart

conducting interviews

facilitating focus group

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The role of the project manager includes

leading the team that is responsible for achieving the project objectives.

leading the human resources department to meet the labor ratio requirements.

leading the functional managers towards reaching the strategic objectives.

all of the above

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is not an input to developing the project charter?

business care

risk management plan

project statement of work

enterprise environmental factors

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is not a project constraint?

schedule

quality

stakeholder

budget

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An approved change request

is an output of the Perform Integrated Change Control process.

can modify the project budget and schedule.

may be a corrective action, a preventative action, or a defect repair.

all of these

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

To create the Work Breakdown Structure, a project manager

lumps together the related work activities to better manage them.

subdivides project deliverables and project work into smaller, more manageable components.

subdivides the project budget to fit each project phase.

lumps together the related project deliverables into larger project phases.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which answer includes the five project management process groups?

initiating process group, performing process group, executing process group, monitoring and controlling process group, and the closing process group

investigating process group, planning process group, estimating process group, monitoring and controlling process group, and the closing process group

initiating process group, planning process group, executing process group, monitoring and controlling process group, and the closing process group

investigating process group, planning process group, deciding process group, monitoring and controlling process group, and the closing process group

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?