SCRUM Debriefing Test

SCRUM Debriefing Test

Professional Development

•

26 Qs

quiz-placeholder

Similar activities

HTML & CSS quiz

HTML & CSS quiz

6th Grade - Professional Development

•

21 Qs

Modern technologies

Modern technologies

Professional Development

•

21 Qs

Introduction to AI Quiz

Introduction to AI Quiz

Professional Development

•

21 Qs

CompTIA A+ 220 Core 1 (RAM)

CompTIA A+ 220 Core 1 (RAM)

Professional Development

•

21 Qs

Anime

Anime

5th Grade - Professional Development

•

21 Qs

A+ - 19C - Explain Data Handling Best Practices

A+ - 19C - Explain Data Handling Best Practices

Professional Development

•

21 Qs

N5 - HTML + CSS

N5 - HTML + CSS

6th Grade - Professional Development

•

22 Qs

Multiverse of Computers

Multiverse of Computers

4th Grade - Professional Development

•

22 Qs

SCRUM Debriefing Test

SCRUM Debriefing Test

Assessment

Quiz

•

Computers

•

Professional Development

•

Hard

Created by

Lazaro Alsina

Used 23+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

26 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What is recommended size for The Development Team (within the Scrum Team)?

9

Minimal 7

7 +/- 2

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who should know the most about the process toward a business objective or a release, an be able to explain the alternatives most clearly?

The Scrum Master

The Product Owner

The Development Team

The Project Manager

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When the Sprint is over?

When all Product Backlog items meet their definition of done

When the time-box expires

When all the tasks are completed

When the product Owner says it is completed

4.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

What questions should be answered in the stand-up meeting?

What will I do today?

What did I do yesterday?

Do I see any impediment?

What worked well?

What could be improved?

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What happens during Sprint 0?

Overall planning, base system architecture, base design, version control and continuous integration setup.

Establish base system architecture and design, install version control and continuous integration setup.

Base system architecture and design.

There is no such thing as Sprint 0.

Requirements gathering, version control setup, and continuous integration setup.

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The time-box for a Daily Scrum is?

15 minutes for a 4 week sprint. For shorter Sprints it is usually shorter.

Two minutes per person.

4 hours.

15 minutes.

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Who has the authority to cancel a Sprint?

Product Owner

Scrum Master

Development Team

All roles togethe

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?