1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Which of the following is TRUE about a work breakdown stucture?

It contains work packages that are descibed in a linear, unstuctured list.

Each item in the WBS represents a feature in the product scope

The WBS represents all of the work that must be done on the project.

The WBS is created by the product sponsor and stakeholders.

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Which is NOT an output of a Scope Management process?

Business case

WBS dictionay

Change requests

Accepted deliverables

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

What is the corect order of the Scope Management processes?

Plan Scope Management, Define Scope, Create WBS, Collect Requirements, Validate Scope, Control Scope

Plan Scope Management, Collect Requirements, Control Scope, Create WBS, Validate Scope

Plan Scope Management, Collect Requirements, Define Scope, Create WBS, Validate Scope, Control Scope

Plan Scope Management, Collect Requirements, Baseline, Define Scope, Control Scope, Validate Scope

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

The goal of Validate Scope is:

To inspect the scope statement for defects so that it is corect

To gain fomal acceptance of the project deliverables from the sponsor and stakeholders

To get eveyone in the project working together toward a common goal

To veify that all PMBOK Guide processes are complied with

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Histoical infomation and lessons leaned are pat of

Organizational process assets

Enterpise environmental factors

Project management infomation system PMIS

Work pefomance infomation

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

You’ve taken over as a project manager on a highway constuction project, and the execution is already under way. Your sponsor tells you that moving foward, all asphalt should be laid down with a 12” thickness. The scope statement and the WBS call for 9” thick asphalt. What is the BEST course of action?

Look for a cheaper supplier so the cost impact is minimized.

Tell the sponsor that the work is already under way, so you can’t accommodate his request.

Refuse to alter the plans until the change control system has been used.

Tell the team to accommodate the request immediately.

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Which of the following BEST descibes the purpose of a requirements traceability matix?

It descibes how WBS dictionay enties are traced to work packages, and how work packages are decomposed from deliverables.

It’s used to make sure that all of the subplans of the Project Management plan have been created.

It helps you understand the source of each requirement, and how that requirement was veified in a later deliverable.

It’s used to trace the source of evey change, so that you can keep track of them through the entire Control Scope process and veify that the change was properly implemented.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?