1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A project manager is currently using data analysis techniques to develop work performance information to compare the work performed so far against the project schedule. Which of the following processes is the project manager currently carrying out?

Control Schedule
Estimate Activity Durations
Develop Schedule
Estimate Activity Resources

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

You are working with your project team to identify and document the specific actions to be performed to produce the project deliverables. Which of the following do you need before you can start this process?

Scope baseline
Issue log
Risk register
Activity list

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Based on the characteristics of the project, the project manager suggests selecting an agile method that limits the number of tasks being worked on by the team members at any given time. This method will also allow the team to increase the visibility of issues and bottlenecks in their work process. Which of the following methods does the project manager suggest?

kanban
scrum
crystal
kaizen

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Agile team members have determined the upper and lower control limits for the velocity required to meet their product release date. So far, the team performed somewhere around the mean, however, in the previous iteration the team’s velocity went way below the lower control limit. What should the team do next?

Explain to the product owner that they cannot make their release date
Try their best to make better than average progress in subsequent iterations
Decrease the number of story points to which they commit in each iteration
Increase the amount of work in progress in the next iteration

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

During a software development project, developers spent two days to repair a defect that was found a day earlier. The<br />deployment team then spent another day to deploy the fix at the customer premises.<br />Which of the following does this four-day period represent?

Lead time
actual time
cycle time
response time

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

To create a schedule model for project execution and monitoring and controlling, you analyze activity sequences, durations,<br />resource requirements, and schedule constraints.<br />What would be the most likely outcome of the process you are performing?

Schedule management plan
Monte Carlo probability distribution
Detailed Gantt bar chart
Schedule forecasts

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A development project is behind schedule, and the project manager finds a way to bring the schedule back into alignment with the plan. The testing of the software code is scheduled to start one week after the coding is complete, so the project manager adjusts the timeline to have the software testing begin immediately after the coding is complete. What tool or technique has the project manager used to get the schedule back on track?

Crashing Fast tracking Leads and lags

Fast tracking

Leads and lags

Earned value management

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?