Resource Mgmt Pre-test

Resource Mgmt Pre-test

Professional Development

10 Qs

quiz-placeholder

Similar activities

Microsoft 365

Microsoft 365

Professional Development

11 Qs

SLS PS 2.0 Types of Learning Experiences (LE)

SLS PS 2.0 Types of Learning Experiences (LE)

Professional Development

10 Qs

Pivot Tables

Pivot Tables

Professional Development

10 Qs

Design Basics of Substation  engineering

Design Basics of Substation engineering

Professional Development

10 Qs

Soal PPPK Pedagogik 4

Soal PPPK Pedagogik 4

Professional Development

15 Qs

Trg@home 1

Trg@home 1

Professional Development

10 Qs

Pre and Post Test

Pre and Post Test

Professional Development

10 Qs

Pre & Post Test QCC

Pre & Post Test QCC

Professional Development

10 Qs

Resource Mgmt Pre-test

Resource Mgmt Pre-test

Assessment

Quiz

Professional Development

Professional Development

Practice Problem

Medium

Created by

Moises Quezada

Used 3+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

A team member has missed the last two team meetings. Several of his assigned deliverables were completed late, and not all were of acceptable quality. He requests a meeting with the project manager, where he explains that he has been dealing with a number of personal issues, which he realizes have affected his work. Although this has been concerning for the project manager, as he has had to smooth the irritation of other team members and even taken on some of the team member's responsibilities, the project manager shows concern to the team member. He works with the team member to reschedule his work to allow him long weekends to deal with his personal situation and still get his activities on time. This is an example of:

Expectancy theory

Theory Y management

Emotional intelligence

Problem-solving

2.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

A project is being completed by a virtual team with team members from six countries. From their various locations, the team members are arguing about which office will take the lead on the project, disagreeing over meeting schedules, and questioning the abilities of individuals whom they have not worked with before. In which stage of the Tuckman ladder is this team functioning?

Forming

Reforming

Storming

Resourcing

3.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

Many work packages have been successfully completed on the project, and the sponsor has made some recommendations for improvements. The project is on schedule to meet an aggressive deadline when the successor activity to a critical path activity suffers a major setback. The activity has 14 days of float and is being completed by four people. There are two other team members with the skill to assist the troubled activity, if needed.

The project manager finds out that three other team members are attempting to be removed from the project because they do not feel the project can be successful. When the project manager investigates, she discovers that those team members have issues that have not been addressed. Which of the following is the best thing to do to improve the project?

Have the team members immediately assist the troubled activity.

Investigate why the project schedule is aggressive.

See who can replace the three team mebers.

Create an issue log.

4.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

During the first half of the project, five team members left for other projects without being replaced, two team members went on vacation without informing you, and other team members expressed uncertainty about the work they were to complete. In this situation, it is best if you update which of the following for the second half of the project?

Communication

management plan

Resource

histogram

Resource

management plan

Responsibility

assignment matrix

5.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

The project has been challenging to manage. Everyone has been on edge due to pressure to complete the project on time. Unfortunately, the tension has grown to the point where team meetings have become shouting matches, with little work accomplished during the meetings. One team member asks to be excused from future team meetings, as all the shouting upsets him. Meanwhile, the sponsor has expressed interest in attending future team meetings to hear how the project is going and to better understand the issues involved in completing the project. In addition, the customer has started discussions about adding scope to the project. In this sitaution, it would be best for the project manager to:

Ask the sponsor if the information needed could be sent in a report rather than have her attend the meetings.

Inform the team member who asked to be excused from the meetings of the value of communication in such meetings.

Involve the team in creating new ground rules for the meeting.

Hold a team-building exercise that involves all the team members.

6.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

The installation project has a CPI of 1.03 and SPI of 1.0. There are 14 team members, and each team member had input into the final project management plan. The customer has accepted the three deliverables completed so far without complaint, and the responsibility assignment matrix has not changed since the project began. The project is being completed in a matrix environment, and there are no contracts needed for the project.

Although the sponsor is happy with the status of the project, one of the team members is always complaining about how much time his project work is taking, Which of the following is the best thing for the project manager to do?

Review the reward system for the project.

Try to improve schedule performance of the project.

Meet with teh customer to try to extend de schedule.

Gain formal acceptance in writing from the customer.

7.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

You just found that a major subcontractor for your project consistenly provides deliverables late, The subcontractor approaches you and asks you to continue accepting late deliverables in exchange for a decrease in project costs. This offer is an example of:

Confronting

Compromise

Smoothing

Forcing

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?