1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are analyzing the data in a control chart to determine the variance in a process that has been implemented to reduce the number of defective components produced by a specific business unit. You notice that although none of the charted data points fall outside of the defined control limits, there are seven consecutive points that have been recorded very close to the upper control limit. Which of the following is true about your control chart results?
a. If the data points are not trending upward or downward the process is considered to be in control and monitoring should continue. No other action required.
b. The process is in control.
c. The chart indicates a specific situation that requires investigation and corrective action.
d. The results are inaccurate and precise.

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Your team is developing a new process to provide marketing for your company’s new product. There is much uncertainty, complexity, and risk in the development portion, followed by a defined, repeatable rollout phase. You explain to your sponsor that you must record this in the project management plan as your :
A. Development approach, hybrid
B. Development approach, predictive
C. Development management plan, hybrid
D. Development management plan, incremental

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Your project teams work in various locations that are scattered throughout the globe with little opportunity to meet face-to-face. As such, you have set up virtual teams using video communications software in order to enable communications and engage the team. Virtual team meetings are useful for all of the following except:
A. Cultural exchange
B. Knowledge sharing
C. Team building
D. Resolving conflict

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

User stories are short textual descriptions of requirements. They are used to stimulate conversation about what functionality is required. They describe all of the following except:
A. The stakeholder role
B. How long it will take to develop the story
C. What the stakeholder needs to accomplish
D. Who benefits from the feature

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Your team is using a probability impact matrix. The scales on each axis of the matrix are labelled Very High, High, Moderate, Low, and Very Low. Your team is using:
A. An ordinal scale
B. A cardinal scale
C. SWOT analysis
D. Quantitative risk analysis

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are a project manager working for the software division of an aerospace company and have been doing waterfall projects for many years. Since you are also a certified Scrum Master, you have been asked to oversee several traditional waterfall projects and several scrum teams. You have decided to use a bar (Gantt) chart to track high-level activities across all your teams. The project life cycle you have chosen is called:
A. Predictive, as you are tracking via a bar chart
B. There is not enough information in the question
C. Agile, as its use in some of the projects supersedes waterfall
D. Hybrid, as it incorporates both waterfall and agile

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Project managers must develop skills to get things done. This means developing an understanding of formal and informal structures of all organizations involved in the project. An understanding of power and politics is also required. Understanding all of these elements will assist in improving the project manager's:
A. Formal reporting process
B. Influencing skills
C. Upward communication
D. Writing style

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?